1. Road Future Projects
Project Proposed Base Cost
Location Description Project Description Planning Basis Cost Basis
ID Timing Estimate
• 1516T017 Dr Pages Road
Dr Pages Rd / Kinmond Creek • Upgrade gravel road sections to sealed and Kinmond Creek Road
Road upgrade, sealing &
R-1 Rd standard 2014-2016 $4,659,830 Upgrade Construction
improvement in flood immunity
(Cootharaba) • PIP (16 September 2013) • Capital Works
Program2015-2016
• 1617T112 Kinmond Creek -
Kinmond Creek Rd Sandy Creek & Eastern Branch Creek • 1617T112 Kinmond Creek - Council Council Report v5
R-2 2016-2021 $1,601,732
(Cootharaba) culvert and road capital reconstruction Report v5 • Capital Works Program
2017-2018
Ernest St / Hilton Tce • Extract - 5 Year Capital
R-3 Upgrade T intersection to roundabout • Noosa Traffic Study to 2036 2016-2021 $3,000,000
(Tewantin) Works Program 2017-2019
Poinciana Ave / Moorindil St • Cost Estimate – Attachment
R-4 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2016-2021 $568,224
(Tewantin) R-5
Memorial Ave / Doonella St • Cost Estimate – Attachment
R-5 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2016-2021 $568,224
(Tewantin) R-5 (Similar project scope)
Gibson Rd / Eumundi Noosa • Cost Estimate – Attachment
R-6 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2016-2021 $568,224
Rd (Noosaville) R-5 (Similar project scope)
Butler St / Poinciana Ave • Cost Estimate – Attachment
R-7 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2016-2021 $568,224
(Tewantin) R-5 (Similar project scope)
Heron St / David Low Way • Cost Estimate – Attachment
R-8 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2021-2026 $568,224
(Peregian Beach) R-5 (Similar project scope)
David Low Way / Lowry St / • Extract - 5 Year Capital
Upgrade 4 way intersection to
R-9 Peregian Esplanade • Noosa Traffic Study to 2036 2021-2026 $3,000,000 Works Program 2017-2019
roundabout
(Peregian Beach) (similar project scope to R-4)
Walter Hay Dr / Eenie Creek • Cost Estimate – Attachment
R-10 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2021-2026 $568,224
Rd (Noosaville) R-5 (similar project scope)
Walter Hay Dr / Eumundi • Cost Estimate – Attachment
R-11 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2021-2026 $568,224
Noosa Rd (Noosaville) R-5 (similar project scope)
• Eenie Creek Road Stage
3_7009-11-Overall Estimate
(June 2006) (assumed
Ben Lexcen Dr / Eenie Creek
R-12 Upgrade signalised intersection • Noosa Traffic Study to 2036 2021-2026 $1,443,600 similar project scope to
Rd (Sunshine Beach)
original intersection +
signalling components
indexed to 2014 base date)
Eumundi Noosa Rd / Eenie • Cost Estimate – Attachment
R-13 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2021-2026 $568,224
Creek Rd (Noosaville) R-5 (similar project scope)
Reef St / Mary St • Cost Estimate – Attachment
R-14 Upgrade roundabout capacity • Noosa Traffic Study to 2036 2021-2026 $568,224
(Noosaville) R-5 (similar project scope)
3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.