001 ECM_21713731_v5_Negotiated Decision Notice OPW21 0134 · OPW21/0134.02
18. All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
asphaltic concrete, unless other pavement types are approved as feature areas in
intersection thresholds, speed control devices, turning areas, indented parking etc.
19. The installation and/or modification of any traffic signs, street signs, line marking and Raised
Reflective Pavement Markings (RRPMs) must be in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD). New or relocated signage must be installed using the VLok
installation system. All new signage must be Class 1 retroreflective material in accordance
with AS 1906.1, Retroreflective materials and devices for road traffic control purposes – Part
1: Retroreflective sheeting.
20. The developer must notify Council’s Traffic Engineer for any works involving the removal or
modification of existing Council traffic signs prior to such works commencing.
Pavement Design and Construction
21. The pavement design for the reconstruction of Lake Weyba Dr is not approved. To attain
approval for the pavement design, the following details must be submitted and certified by
an RPEQ with the proposed pavement design:
a. The design CBR must be based on the four day soaked CBR value for the subgrade
material;
b. The design subgrade CBR must be representative of each homogenous insitu section
of finished subgrade. With respect to each section:
i. For four or less test results, the design CBR must be taken as the least estimated
insitu CBR result.
ii. For five or more test results, the design CBR must be taken as the 10th percentile
of all estimated insitu CBR results.
c. The samples must be taken generally in the position of the outer wheel path on both
sides of the proposed road. A sketch plan showing the location of all tests must be
submitted with the test results for pavement design approval; and
d. Where imported material has been (or is proposed to be) used for subgrade
replacement, and the depth of the imported material is less than 300mm, the pavement
design CBR must be based on the testing results of the insitu material and not the
imported material.
22. At the time of subgrade inspection, the subgrade must exhibit no visible signs of deformation
under proof rolling by a fully loaded water truck. The pavement subgrade will not be passed
until this requirement has been achieved.
23. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
24. Safe pedestrian access on all streets in the vicinity of the development must be maintained
at all times. Should footpath/road closures be necessary to carry out construction works,
Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
25. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
26. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Page 5 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001 ECM_21713731_v5_Negotiated Decision Notice OPW21 0134.pdfRelated documentApplication case desk ↗
About this file
- File size
- 220 KB (small file)
- File type
No other editions are linked here.