Town Planning Assessment Report · MCU25/0020
driveway.
Bushfire Hazard Management AO15 Within a bushfire hazard Not applicable
PO15 Where located in a Bushfire area where there is no reticulated
Hazard Area as shown on the water supply, the premises has:
Bushfire Hazard Overlay Map in 1. an accessible dam,
Schedule 2 and not in a water swimming pool or water tank
service area, an adequate, reliable, available for firefighting purposes
safely located and freely accessible with an onsite water volume of not
water supply is provided for fire less than 5,000 litres; and
fighting purposes, which is in 2. a water supply outlet pipe
addition to day to day water supply. 50 millimetres in diameter and
fitted with a standard fire brigade
fitting connected to the water
supply (other than where the water
supply is in a swimming pool or
dam).
Editor’s Note — Water supply
capacity for firefighting purposes is
in addition to water supply capacity
for household use.
Flood Hazards AO16.1 Where the development is Alternate Solution
PO16 Development is designed located in the Flood Hazard Area as Alternative Solution
and sited to ensure risk to people shown on Flood Hazard Overlay Refer Proposal Plans and
and property from flooding is Map in Schedule 2, the finished Section 6.2 of report.
avoided or minimised. floor level of habitable rooms is at
least 300 millimetres above the
Defined flood event (DFE).
OR
AO16.2 Where the DFE has not
been modelled for the area, the
finished floor level of habitable
rooms is at least 500 millimetres
above the highest recorded flood.
Editor's Note—The QDC mandatory
provisions MP3.5 also apply to the
construction of buildings in flood
hazard areas.
Major Electricity Infrastructure AO18.1 Development including any Not applicable
& Substations sensitive land uses is at least: The site is not mapped as
PO18 Development is sufficiently 1. 50 metres from a containing major electricity
separated from major electricity transmission substation; infrastructure or substations.
infrastructure and substations to 2. 10 metres from any other
minimise the likelihood of nuisance substation; and
38
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Town Planning Assessment Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 8.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.