RFI - Appendix D- Stormwater Management Plan · MCU22/0140
Plans and drawings: the text below has words only, no drawings.
Rational Method Calculations
Project 215101
Address 7 Ruby Street By DK
Pre - Development Post - Development
Catchment Details Catchment Details
Area 0.1012 ha Area 0.1012 ha
fi 0.27 fi 0.49
C10 0.75355731 C10 0.7986166
I10 70.2 mm/hr I10 70.2 mm/hr
Standard Inlet Time Standard Inlet Time
Time 5 mins Time 4 mins
Overland Sheet Flow (Friend's Eqn) Overland Sheet Flow (Friend's Eqn)
Length m Length m
Slope % Slope %
Surface 'n' Surface 'n'
Time 0 mins Time 0 mins
Pipe Flow Travel Time Pipe Flow Travel Time
Flow Distance m Flow Distance m
Fall of Channel m Fall of Channel m
Time mins Time mins
Kerb Flow Kerb Flow
Length m Length m
Slope % Slope %
Time 0.0 mins Time 0.0 mins
Channel Flow (Figure 4.8 QUDM, or Channel Flow (Figure 4.8 QUDM, or
Manning's Equation) Manning's Equation)
Flow Distance m Flow Distance m
Fall of Channel m Fall of Channel m
Time mins Time mins
Adopted Time of Adopted Time of
Concentration
5 mins Concentration
5 mins
Pre-Development Peak Discharges Post-Development Peak Discharges
Design Storm Frequency
Area (ha) Cy Iy (mm/h) Qy (m3/s) (AEP) Factor (Fy)
Area (ha) Cy Iy (mm/h) Qy (m3/s)
0.1012 0.60284585 120 0.02 63.20% 0.80 0.1012 0.63889328 120 0.022
0.1012 0.64052372 150 0.027 39.35% 0.85 0.1012 0.67882411 150 0.029
0.1012 0.71587945 187 0.038 18.14% 0.95 0.1012 0.75868577 187 0.04
0.1012 0.75355731 215 0.046 10% 1.00 0.1012 0.7986166 215 0.048
0.1012 0.79123518 245 0.054 5% 1.05 0.1012 0.83854743 245 0.058
0.1012 0.86659091 286 0.07 2% 1.15 0.1012 0.91840909 286 0.074
0.1012 0.90426877 316 0.08 1% 1.20 0.1012 0.95833992 316 0.085
Discharge Comparison
AEP 63.20% 39.35% 18.14% 10% 5% 2% 1%
Difference 0.002 0.002 0.002 0.002 0.004 0.004 0.005
Percentage 10.0% 7.4% 5.3% 4.3% 7.4% 5.7% 6.3%
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RFI - Appendix D- Stormwater Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.