whichever is the sooner. Payment of deferred headworks contributions shall also be
subject to the following requirements:-
29.2.4 Payment of a bonding fee in the amount of $150 and submission of a
trading bank guarantee to the value of headworks assessed at the time
of submission, plus 20%, prior to the issue of a Development Permit
for building works;
29.2.5 Headworks shall be calculated as the value of headworks assessed at the
ordinarily due time of payment, plus interest charged at the rate set by
the Queensland Treasury Corporation for Local Government
borrowings as they apply to Noosa Shire. The interest rate used shall
be the rate current at the "time prescribed" above;
29.2.6 Should the contributions not be paid at the due time, Council shall call
upon the security lodged; and
in the case of a Development Permit for building works, if a permit expires the
securities will be returned.
30. The footpath across the Hastings Street frontage of the site is to be fully landscaped
from the kerb and channel to the property alignment to the satisfaction of the Shire
Engineer.
The pavement is to be designed and constructed to ensure pedestrian safety using non-
slip materials and to produce an evenly graded surface finish.
31. The developer will remove the existing dining facilities in The Parade. This area will be
reinstated to a suitable public area and landscaped to the requirements and satisfaction
of the Shire Engineer. Landscaping plans required by Condition 2 are to also address
this area.
32. The developer shall contribute toward, roadworks and landscaping improvements in the
Hastings Street locality in the amounts set out below. Such contributions shall be paid
prior to the issue of a Building Permit:-
Roadworks $24,000
Landscaping $12,000
33. The developer is to construct the basement carpark floor level to a minimum of 2 metres
AHD. This change in design is to be incorporated into the design of the ramp into the
carparking module, as well as in all other design drawings.
34. The developer shall bear the cost of alteration of any public utility or other facilities
necessitated by the development of the land or associated construction works external to
the site.
c:\users\noo.ecm.prod.web.svc\appdata\local\temp\4894c4ec-8cdd-4444-be14-b0cba2d65697.doc
Print Date: 10 December 2018, 9:45 AM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix F - Council Report - Change Application 28.2.19.pdfRelated documentApplication case desk ↗
About this file
- File size
- 494 KB (small file)
- File type
No other editions are linked here.