CHANGE - Maple St Change and Response 20.04.2026
Figure. 2 – 2008 parking arrangement with access driveway.
d. Subdivision Timing
The application seeks for any approval conditions to allow for the subdivision sealing of the
two lots, prior to the construction of the development being finalised. The frontage works
associated with the driveway access will be undertaken as part of the initial Operational
Works for frontage works, with all services and stormwater discharge to be obtained via
the street, or an easement to be created to ensure the standalone lots may function
independently.
e. Engineering, Landscaping and Waste Management
Recor have provided a detailed stormwater management and engineering plans, including
earthworks, frontage works and drainage layouts. The layouts are largely the same as the
previously supported driveway and benching layouts, except that bioretention basins have
been replaced with detention tanks and treatment systems.
The changes have allowed for more deep landscaping areas to be provided along the
southern boundary of the site, to ensure the built form follows the natural contours of the
site. Detailed sections are provided along the southern boundary to demonstrate how buffer
landscaping will screen the third storey encroachment for a section of the building within
the middle of the site. Coordination between the architecture, landscaping and engineering
design has ensured the protection of amenity to adjoining residential premises.
Figure. 3 – Engineering and Landscape Plan
Page 5 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (CHANGE - Maple St Change and Response 20.04.2026.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.