response to information request - 38 mossman 21.05.24 · MCU24/0032

of 5

Text shows just the words. Original shows the document exactly as it was published.

   6. Provide amended plans that complies with the site cover requirements of the
      Noosa Plan 2020.

Amended site cover plans are provided demonstrating compliance with the 50% and 30%
site cover requirements for dwelling houses on each storey and in accordance with the
planning scheme definition, which should only account for the voids as a single storey.




Figure. 4 Site Cover drawings and relevant Noosa Plan definitions.


   7. Provide amended architectural drawings with setbacks that comply with the
      requirements of the zone code.
   8. Noting that Council will not support the basement (including piling and any
      associated works) encroaching into the boundary setback areas, provide
      amended architectural drawings with setbacks that comply with the
      requirements of the zone code.
   9. Provide an amended landscaping plan calculated in accordance with the
      Noosa Plan 2020 definition of soft landscaping.

Amended plans are provided with increased setbacks for the basement and shoring to
allow for landscaping around the perimeter of the building. The revised landscaping plans
provide for meaningful and deep landscaping, with conditions to be applied for size and
location of landscaping trees.

   10. Provide floor plans and elevations of the proposed dwelling demonstrating
       that habitable floor levels can be provided in accordance with Table 8.2.6.4
       of the Flood Hazard Overlay Code.

The floor levels are designed above the 2.7m AHD minimum floor levels.

   11. Provide an updated site-specific Dewatering and Acid Sulfate Management
       Plan prepared by a suitably qualified person. The updated plan must
       reference the proposed development plans and demonstrate how Acid
       Sulfate affected water encountered during construction will be treated and
       disposed of.

                                                                            Page 3 of 5

Used in these records

About this file

File size
1.4 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

response to information request - 38 mossman 21.05.24.pdf · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.