b. has a degree in civil engineering or engineering geology; and
c. has a minimum of 5 years experience in the field of geotechnical engineering or
engineering geology.
5. For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
landscape architect, landscape designer or horticulturalist with a minimum of 3 years
current experience in the field of landscape design.
6. For the purpose of preparing an Arborist Report, a qualified person is considered to be a
person with either:
a. ISA certification; or
b. a Diploma of Arboriculture in addition to a minimum of 3 years current experience in the
field of arboriculture.
Sustainability
7. Council encourages sustainable and energy efficient building design for all development,
including the use of sustainable building materials, energy efficient fittings, solar hot water,
photovoltaic systems (including the use of inverter/charges), solar panels, water saving
devices and rainwater harvesting.
Performance Bond
8. Where the works include Council assets (construction of new or modification to existing) a
portion of the performance bond will be retained as a “maintenance bond” as described in
Council’s Planning Scheme Policy 6 Engineering Design Standards. Alternatively, the
developer may submit a separate “maintenance bond” at the completion of work.
The bond amount will be
a. 5% of the agreed value of the works or
b. $1500, whichever is the greater amount
Preparation of a Preliminary Construction Management Plan
9. A preliminary Construction Management Plan must be submitted with the Operational
Works application and must address the following:
a. A Traffic Management Control Plan in accordance with the Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control measures
prior to construction.
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction.
ii. maintenance of safe pedestrian access for the areas affected by the works
during and after daily construction has ceased.
iii. proposed fencing to the site during the construction phase of the
development.
iv. approval of the Traffic Management Control Plan by the Department of
Transport and Main Roads (DTMR) for any works on State controlled roads.
v. provision for worker car parking.
b. Maintenance and protection of water quality and existing drainage lines through the
10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.