ORDINARY MEETING AGENDA 20 JUNE 2019
Waste Disposal
41.42. The developer must provide waste storage and disposal facilities in
accordance with Planning Scheme Policy No. 9 “Waste Management Multi-
Dwellings and Commercial and Industrial Premises”. The facilities must include an
impervious area, within the site, correctly sized for all refuse and recycling
containers and suitably screened from public places and neighbouring properties.
A bin wash area is required with a cold-water tap, hose and drain outlet connected
to sewer, via a bucket trap. The drain outlet must be designed to prevent storm
water entry to the sewerage system.
42.43. Refuse containers must be provided in accordance with the requirements of
the Environmental Protection (Interim Waste) Regulation 1996 and (Waste
Management) Regulation 2000, for the storage and collection of refuse.
43.44. Public bins must be provided throughout the car park to reduce littering. Bins
provided must be for refuse and recycling and be decanted into the bulk bins by
the site operators.
44.45. Service vehicle parking, manoeuvring and standing space along Diamond
Lane must be provided in accordance with the approved plans. The works must be
undertaken in accordance with an Operational Works approval.
RECONFIGURING A LOT
When Conditions Must Be Complied With
45.46. Unless otherwise stated, all works required by the conditions of this Decision
Notice must be completed prior to submission of the subdivision plan to Council for
compliance assessment.
Approved Plans
46.47. Development undertaken in accordance with this approval must generally
comply with the approved plans of development. The approved plans are listed in
the following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA-16.0518.2A A Site plan/Ground floor plan April 2019
47.48. All lot numbering on the subdivision plan to be submitted to Council for
compliance assessment must remain as shown on the Approved Plans.
Dedication
48.49. The submitted Plan of Survey shall include a two (2.0) metre wide strip
extending across the full length of the frontage to Diamond Lane is to be dedicated
to Council as ‘Road’.
Water & Sewer Connections
49.50. An underground connection to reticulated water and sewerage must be
provided to each lot in accordance with the standards and requirements of
Northern SEQ Distributor–Retailer Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection
to reticulated water and sewerage has been provided to each lot.
Page 27 of 33