Referral Agency Response - Planning RAP23 0011 · RAP23/0011

of 7

Text shows just the words. Original shows the document exactly as it was published.

                 11.    Existing vegetation in the road reserve must be retained, unless written authorisation
                        from Council is granted for the clearing.
                 12.    Trees to be retained must be protected from clearing or construction activities by:
                        a.      clearly marking vegetation to be retained with flagging tape
                        b.      installing protective fencing around the drip line of the vegetation
                        c.      restricting stockpiling, storage and vehicle parking to those areas which are
                                already cleared
                        d.      using low impact construction techniques around vegetation.
                 13.    All planting areas on the eaves must be planted and maintained at all times, with
                        replacement planting undertaken promptly where plants fail or do not have a healthy
                        and vigorous growth.
                        Stormwater Drainage
                 14.    Stormwater runoff from the development must be disposed of without causing scour or
                        damage to the subject site or any adjoining property.
                        Easements
                 15.    Unless otherwise agreed in writing by the relevant service provider, any public or third
                        party infrastructure located on the subject site must be placed within an easement
                        registered against the title of the property.
                 16.    All easements must be designed in accordance with the planning scheme and granted
                        at no cost to the Grantee. Where the Grantee is Council or a service authority, the
                        easement documentation must be in accordance with the Grantee’s standard easement
                        terms. Draft easement documentation must be submitted to Council for endorsement.
                 17.    All works must be kept clear of any existing or proposed easements on the subject land,
                        unless agreed otherwise in writing by the Grantee.
                        Geotechnical Stability
                 18.    All works must be carried out in accordance with the recommendations contained in
                        section 6 of the Report on Geotechnical Investigation prepared by Douglas Partners
                        dated October 2021.
                        Earthworks and Retaining Walls
                 19.    All earthworks and associated retaining structures/batters, both above and below
                        ground, both temporary and permanent, must be contained entirely within the subject
                        site unless written permission form the respective landowner(s) is provided to Council.
                        All earthworks must be undertaken in accordance with the provisions of Australian
                        Standard AS3798: Guidelines on Earthworks for Commercial and Residential
                        Developments.
                 20.    Where the development involves excavation or filling over, or adjacent to, drainage,
                        water supply or sewerage infrastructure, all access chamber surface levels must be
                        adjusted to provide a freeboard of 100mm above the finished ground surface level.
                 21.    All retaining walls must be designed and constructed in accordance with the planning
                        scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
                        walls that are publicly accessible and exceed 1.0m in height must be fitted with a
                        commercial grade safety fence.
                 22.    Prior to the issue of a Building Permit, the supervising RPEQ must certify that the
                        earthworks have:




                                                                                                         Page 4 of 7
Document Set ID: 22877932
Version: 5, Version Date: 22/03/2024
Log in to download the original file

Referral Agency Response - Planning RAP23 0011.pdf · 123 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.