PROPOSED COMMISSIONING PLAN
Proposed only and subjected to change by Energex.
LV SWITCHING SHEET:
1. INSTALL LV UG NETWORK AS PROPOSED, DO NOT
CONNECT NEW 16 LV UG TO 120 LV UG AT U5804 (STN 1)
2. OPEN SC21301-A/FS1 FUSE SWITCH AT SC21301
3. CONNECT NEW 16 LV UG TO 120 LV UG AT U5804 (STN 1)
4. CLOSE SC21301-A/FS1 FUSE SWITCH AT SC21301
5. TEST AND COMMISSION
6. CONDUCT POST COMMISSIONING CHECKS
Where interruptions are proposed, customers
shall be notified as per Energex requirements.
24191
Parth Patel
RPEQ 21483
2025.02.05 15:08:07
+10'00'
ABN 12 115 160 748
Phone (07) 5479 1368
E-mail: [email protected] PO Box 807
Website: www.millwell.com.au Maroochydore QLD 4558 © This design and drawing is copyright and is not to be used or reproduced
wholly or in part without written permission of Millwell Services Pty Ltd
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original