SUPERSEDED - Amended Decision Notice - MCU22 0194 [As Published]
Car Parking
36. A minimum of 7 car parking spaces must be provided on the site. The works must be
undertaken generally in accordance with BAX Engineering’s Siteworks and Drainage Layout
Plan (316-001-300, Rev. B) dated 18 July 2023 and must include in particular:
a. 1 visitor parking spaces within the total; and
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
37. All car parking spaces must be constructed using a suitable concrete pavement or alternate.
38. All vehicles must enter and exit the site in a forward gear.
Stormwater Drainage
39. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval and be generally in accordance with BAX Engineering’s Siteworks and Drainage
Layout Plan (316-001-300, Rev. B) dated 18 July 2023.
40. The development must incorporate water tanks at a minimum of 3,000 litres per dwelling and
may be incorporated in any stormwater management design.
Services
41. Each lot/unit is also subject to compliance with the requirements and approval of any relevant
public service provider (e.g., Unitywater).
42. Underground reticulated electricity and telecommunication services must be provided to
each lot in accordance with the standards and requirements of the relevant service provider.
43. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
44. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Easements
45. A 1.5m wide inter-allotment stormwater drainage easement must be registered against the
title of any property where a stormwater pipeline and/or a secondary flow path conveying
stormwater from another allotment.
46. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
47. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
48. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
49. All fill and associated batters must be undertaken in accordance with an Operational Works
approval, be generally in accordance with BAX Engineering’s Siteworks and Drainage Layout
Plan (316-001-300, Rev. B) dated 18 July 2023, and contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council.
Page 6 of 33
Document Set ID: 22544890
Version: 1, Version Date: 16/08/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.