SUPERSEDED - Amended Decision Notice - MCU22 0194 [As Published]

of 33

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                      Car Parking
               36.    A minimum of 7 car parking spaces must be provided on the site. The works must be
                      undertaken generally in accordance with BAX Engineering’s Siteworks and Drainage Layout
                      Plan (316-001-300, Rev. B) dated 18 July 2023 and must include in particular:
                      a.      1 visitor parking spaces within the total; and
                      b.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities.
               37.    All car parking spaces must be constructed using a suitable concrete pavement or alternate.
               38.    All vehicles must enter and exit the site in a forward gear.
                      Stormwater Drainage
               39.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works
                      approval and be generally in accordance with BAX Engineering’s Siteworks and Drainage
                      Layout Plan (316-001-300, Rev. B) dated 18 July 2023.
               40.    The development must incorporate water tanks at a minimum of 3,000 litres per dwelling and
                      may be incorporated in any stormwater management design.
                      Services
               41.    Each lot/unit is also subject to compliance with the requirements and approval of any relevant
                      public service provider (e.g., Unitywater).
               42.    Underground reticulated electricity and telecommunication services must be provided to
                      each lot in accordance with the standards and requirements of the relevant service provider.
               43.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               44.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               45.    A 1.5m wide inter-allotment stormwater drainage easement must be registered against the
                      title of any property where a stormwater pipeline and/or a secondary flow path conveying
                      stormwater from another allotment.
               46.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               47.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               48.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               49.    All fill and associated batters must be undertaken in accordance with an Operational Works
                      approval, be generally in accordance with BAX Engineering’s Siteworks and Drainage Layout
                      Plan (316-001-300, Rev. B) dated 18 July 2023, and contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.




                                                                                                      Page 6 of 33
Document Set ID: 22544890
Version: 1, Version Date: 16/08/2023
Log in to download the original file

SUPERSEDED - Amended Decision Notice - MCU22 0194 [As Published].pdf · 2.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.