Decision Notice - 010.2009.00001382.001 [As Published] · 142009.1382
Officer: Kevin Slender
Direct Telephone: (07) 5449 5216
Response Address: Locked Bag 72
Sunshine Coast Mail Centre QLD 4560
Email: [email protected]
Our Reference: 2009/1382
Your Reference:
6 January 2010
Oak Investment Holdings Pty Ltd
CARE Mojo Design
PO Box 1261
NOOSA HEADS QLD 4567
Dear Sir
Decision Notice
Integrated Planning Act 1997
I refer to your application and advise that on 5 January 2010 Council decided to approve the
application in full subject to conditions.
Details of the decision are as follows:
1 APPLICATION DETAILS
Application No: 2009/1382
Street address: 43 Elanda Street & 45 Elanda Street SUNSHINE BEACH
Real property description: LOT: 399 RP: 48112, LOT: 400 RP: 48112
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
The following type of approval has been issued:
Preliminary Approval for Operational Works - Landscaping, Carparking & Access,
Frontage Works, Stormwater Drainage & Detention and Infiltration System, Road Widening
and Kerb & Channel, Erosion & Sediment Control
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Preliminary Approval is one year and lapses on 4 January 2011 unless
an application to extend the currency period is approved by Council..
4 ASSESSMENT MANAGER CONDITIONS
1. The applicant is required to lodge a further application for Operational Works in order to obtain
a Development Permit. The Development Permit will be issued upon the payment of
outstanding contributions and bonds required by the conditions of Decision Notice for
MCU 2007/2174 and will be subject to the conditions contained herein. It must also be noted
that no works can commence prior to obtaining a Development Permit.
2. The development shall be carried out in accordance with the approved plans listed below or as
modified herein.
Page 1 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 8 pages
Page 2
2009/1382
3. The management of roof and surface stormwater runoff shall generally be in accordance with
Duke Environmental Management Consultant’s “Stormwater Quantity Management Plan”
AA07731SMP dated Jan 2008.
4. A Traffic Management Plan (TMP) for the development addressing all construction phases
shall be prepared by suitably qualified persons and submitted to Council for approval prior to
the pre start meeting. The TMP shall address, but not be limited to, all items listed below and
shall be flexible in that it addresses all stages of the development.
a. A single nominated access location to and from the site.
b. The plan should detail the routing of trucks to and from the site.
c. Provision of onsite parking for personnel working on this development, as there is
limited parking available in adjacent streets.
d. Provision of safe cycle and pedestrian movements in the vicinity of the development on
Elanda Street.
e. No queuing of trucks is permitted on residential streets, especially prior to 7.00am.
Further parked trucks must have engines turned off.
f. Provision of signage and traffic controllers in accordance with Manual of Uniform Traffic
Control Devices and the Transport Infrastructure (Roads) Act.
g. Provide an indication where the surplus spoil (if any) is to be transported to, and/or the
source of any imported fill material.
5. A 1.5 metre wide concrete footpath shall be constructed across the full frontage of the
development. The alignment shall be determined on site with Council’s Construction Technical
Officer. The footpath shall have a slip resistant surface and the expansion joints shall be “saw
cut”, not trowel jointed.
6. The total required pavement thickness shall be based on the Department of Main Roads’
Pavement Design Manual using soaked CBR tests of the subgrade.
The design pavement thickness, together with CBR test results shall be submitted to Council’s
Chief Executive Officer (CEO) for approval prior to placement of pavement material.
7. All landscaping is to be constructed in accordance with Council’s Planning Scheme Policy
PSP03 Landscaping Plants and Guidelines. Note that the species “Agave attenuate” is not
approved.
8. Suitable root barriers shall be installed where proposed trees are adjacent to paths, pavement,
etc; in accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
Guidelines.
9. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after each
rain event.
These devices are to remain in place during the civil works and construction phases of the
development.
The location and type of device to be installed shall be established at the “pre start” meeting
with Council’s Construction Technical Officer and shall be installed prior to the
commencement of any works.
10. Council’s Construction Technical Officer (phone 0410 512 505) shall be given seven (7)
days’ notice of intention to commence works to arrange a “pre start” meeting prior to
the commencement of those works.
11. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability documentation.
Page 2 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 3
2009/1382
12. Prior to the “pre start” meeting, the principal contractor must be provided with a copy
of Council’s signed approved drawings and conditions by the applicant.
13. The Consulting Engineers for the project shall be currently Registered Professional Engineers
of Queensland (RPEQ). The Consulting Engineers are responsible for arranging all
inspections with Council’s Construction Technical Officer or nominated staff. Council’s
Construction Technical Officer shall provide an inspection form for signing-off by the Engineer
at appropriate stages of construction during on-site meetings. The Construction Technical
Officer will also sign the form at each stage when requested conditions have been satisfied.
The works will be accepted “On Maintenance” after this form has been signed by the
Construction Technical Officer for each stage, and a letter from the Engineer has been
received by Council requesting that the works go “On Maintenance”.
14. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
project. (This person will be the contact for the project).
15. Council standards shall apply to these works unless otherwise modified herein.
16. The person acting on this permit shall ensure that its consultants and contractors take all
reasonable care during the construction of the engineering works to ensure that Council
property, road pavements or facilities (such as underground drainage, water supply,
sewerage, footpaths, kerbing, landscaping, street furniture, etc.) are protected against any
damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its
Consultants or Contractors through any cause whatsoever in the course of, directly or
indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
forthwith notify Council’s CEO and shall forthwith rectify the damage to that property or facility
at its cost and to the satisfaction of Council’s CEO.
All rectification works are to be completed prior to the commencement of the use or,
alternatively, the Applicant may request Council to carry out the rectification work at the
Applicant’s cost, such cost being paid by the Applicant to Council prior to the commencement
of the use.
In the case of any emergency, Council shall be entitled to rectify such damage at the cost of
the Applicant, such cost being paid prior to the commencement of the use.
17. The development of the site shall be carried out in such a manner as to prevent dust and/or
sand nuisance to residents and/or tenants in the vicinity of the development.
18. Construction work and other associated activities are permitted only during the hours of 7.00
am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
except where extended hours are approved by Council’s CEO.
19. Safe pedestrian access in the vicinity of the development shall be maintained at all times. If
footpath / road closures are necessary to carry out construction works, Council’s Construction
Technical Officer (phone 0410 512 505) must be notified prior to the proposed closure.
20. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot “ fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system or natural waterways. Although the sediment and erosion control
measures have been approved, it is the site Supervising Engineer who is responsible for
ensuring that the sediment and erosion control measures have:
i. been duly designed and constructed in accordance with “best practise” methods,
ii. been revised to address the issues raised by any changes to the projected construction
schedule and/or methods,
iii. been revised to address any predicted rainfall events, and
iv. achieved the desired environmental outcomes.
Page 3 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 4
2009/1382
Sunshine Coast Regional Council’s CEO may request further controls to be installed should
approved measures be inefficient.
21. The owners of the subject property shall maintain the grease/oil arrestor pits/gross pollutant
traps in accordance with the manufacturers specifications.
22. The owners of the subject property shall inspect the gross pollutant traps on a weekly basis
and after each storm event.
The owners of the subject property shall enter into an ongoing maintenance contract with a
Registered Contractor to clean and maintain the gross pollutant traps on regular three monthly
cycles and on an “On Call” basis in the case of an emergency.
The management and maintenance of the gross pollutant traps shall be included in the
Community Management Scheme for the completed development.
23. Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement
of satisfactory “As Constructed” records shall be submitted to Council.
As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
(RPEQ) for design intent, and a Licensed Surveyor shall certify the cadastre and the location,
level and type of all services and structures. This information shall be submitted to Council for
checking and for Council’s records.
The data must fully detail levels for all engineering works including, but not limited to, drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. Guidelines on the use of ADAC
are available at www.adac.com.au and Council’s “Noosa Planning Scheme Policy 5 –
Engineering Design Standards – Roads, Drainage and Earthworks”.
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
24. A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will
be imposed on construction works during the maintenance period, which is a minimum period
of 12 months duration. Such bond must be lodged by, and shall only be accepted from the
Developer for the works.
25. The works to become Council assets will not be accepted "On Maintenance" until the
landscaping is completed.
26. These works are also to be in compliance with the relevant conditions of Development Permit
No. 2007/2174.
27. Notwithstanding that Council has checked the plans with due care, where it is found during
construction that variations from Council's standards exist, then Council standards shall apply.
WATER SUPPLY AND SEWERAGE CONDITIONS
28. The existing sewer main within the development site must be capped 1.5 metres from the
existing sewer manhole. This work must be undertaken by Sunshine Coast Water at the
applicants cost.
29. Proposed tree plantings must maintain a minimum horizontal clearance of 1.5 metres from
Council sewerage infrastructure. Landscaping plants within these clearances must be low
growing when mature and suitable Council approved varieties.
30. Stormwater retention systems and gross pollutant traps must maintain a minimum of 1.5
metres horizontal clearance from Council sewerage infrastructure and 1.0 metre from the
sewer house connection.
31. A water service, in accordance with the hydraulic engineers requirements, must be installed
from the existing water main in Elanda street to the property boundary.
32. A water supply enveloper pipe shall be provided under Elanda Street, if required, in
accordance with Sunshine Coast Water requirements.
Page 4 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 5
2009/1382
33. A Council installed primary water meter must be located immediately inside the property
boundary. For community title schemes and commercial sites, the applicant must provide
additional water meters for each separate title or lease area. These meters must be supplied
and installed in accordance with Councils requirements.
34. Existing water connections must be disconnected at the main. Work must be undertaken by
Sunshine Coast Water at the applicants cost.
35. Construction works undertaken in the vicinity of Council's existing water supply or sewerage
infrastructure must not adversely affect the integrity of the infrastructure. All costs associated
with repair, replacement or alteration to existing infrastructure must be met by the applicant.
5 REFERRAL AGENCY CONDITIONS
Not Applicable.
6 APPROVED PLANS
The plans for this preliminary approval are listed in the following table:
Plan No. Rev. Plan Name Date
5083-OPW1 B Locality Plan & Drawing Schedule (by Contour Consulting 18-06-08
Engineers)
5083-OPW2 B Site Plan 18-06-08
5083-OPW3 B Earthworks, Sediment & Erosion Control 18-06-08
5083-OPW4 B Earthworks, Sediment & Erosion Control 18-06-08
5083-OPW5 B External Road & Footpath Works 18-06-08
5083-OPW6 B Internal Driveway & Stormwater Plan 18-06-08
5083-OPW7 B Internal Driveway & Stormwater Details 18-06-08
5083-OPW8 B Detention Basin Plan & Details 18-06-08
L-001 OP2 Key Plan & Drawing Register (by EDAW/AECOM) 11-08-08
L-PP-401 OP2 Planting Plan 11-08-08
L-LE-002 OP2 Legend Specification & Schedule 11-08-08
L-DT-901 OP2 Planting Details 11-08-08
L-DT-902 OP2 Planting Details 11-08-08
L-DT-903 OP2 Planting Details 11-08-08
693-OP1 A Sub Basement Stormwater (by Spice Consulting) 19-08-08
693-OP2 A Level 1 Stormwater (by Spice Consulting) 19-08-08
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1 Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” (Form 2 Development
Application) under the Integrated Planning Act 1997 must be made. Amended plans clearly
indicating the changes must be lodged with this application along with the appropriate fees.
Page 5 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 6
2009/1382
WATER SUPPLY AND SEWERAGE ADVISORY NOTES
2 Connection of the proposed works to existing water supply and sewerage reticulation can only
be performed by Sunshine Coast Water. A quotation for such works will be prepared upon
request.
3 Where connection to the existing reticulation system is required, the depth of the existing
pipework must be determined prior to initiation of works to ensure that the connection can be
made without the use of vertical bends. Approval from Sunshine Coast Water must be
obtained where minimum pipe cover cannot be maintained
4 Council is not responsible for alterations to existing services that may be required when
Sunshine Coast Water is connecting new water mains to the live water network. This may
involve negotiations with other service authorities
5 The house connection branch must terminate at a location no deeper than 1.5 metres from
finished ground level in accordance with Sunshine Coast Water standard drawings SCW 125
and 130.
6 Excavation of the road requires the approval of Sunshine Coast Regional Council Roads and
Drainage Department.
7 Breach of a development condition in respect to erosion and sediment controls may result in
an infringement notice and instant penalty. This can be issued under the authority of the
Environmental Protection (Water) Policy 1977 or the Environmental Protection Act.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not Applicable.
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
A preliminary approval under section 3.1.6 of Integrated Planning Act 1997 has been granted and as
such the level of assessment and applicable codes for any development approval resulting from this
approval are identified in the conditions.
Page 6 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 7
2009/1382
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Operational Works Landscaping, Carparking & Access, Frontage Works,
Stormwater Drainage & Detention and Infiltration
System, Road Widening and Kerb & Channel,
Erosion & Sediment Control
11 SELF ASSESSABLE CODES
Not Applicable.
12 SUBMISSIONS
Not Applicable.
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not Applicable.
14 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).
15 OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully
Mark Lewis
SENIOR ENGINEERING OFFICER - CIVIL ENGINEERING
OPERATIONAL W ORKS ASSESSMENT BRANCH
Page 7 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 8
2009/1382
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
The following is an extract from the Integrated
(6) If an application involves assessment against a
Planning Act (Chapter 4). concurrence agency code, appeal rights for submitters
Division 8 - Appeals to court relating to for the application are not available against the part of
development applications the approval that represents the concurrence agency’s
response for the code.
Appeals by applicants
Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application
may appeal to the court against any of the following- 4.1.29.(1) An advice agency may, within the limits of
its jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development development approval for a development application
application; if-
(b) a matter stated in a development approval, (a) the development application involves impact
including any condition applying to the assessment; and
development, and the identification of a code
under section 3.1.6;1 (b) the advice agency told the applicant and the
assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for;
(2) The appeal must be started within 20 business
(d) the length of a relevant period; days after the day the decision notice or negotiated
(e) a deemed refusal. decision notice is given to the advice agency as a
(2) An appeal under subsection (1)(a) to (d) must submitter.
be started within 20 business days (the “applicant’s Appeals for matters arising after approval given
appeal period”) after the day the decision notice or (co-respondents)
negotiated decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
(3) An appeal under subsection (1)(e) may be development application, a person to whom any of the
started at any time after the last day a decision on the following notices have been given may appeal to the
matter should have been made. court against the decision in the notice-
Appeals by submitters (a) a notice giving a decision on a request for
4.1.28.(1) A submitter for a development application extension of the relevant period for an approval;
may appeal to the court about- (b) a notice giving a decision on a request to make a
(a) the giving of a development approval, including minor change to an approval.
any conditions (or lack of conditions) or other (2) The appeal must be started within 20 business
provisions of the approval; or days after the day the notice of the decision is given to
(b) the length of a relevant period for the approval. the person.
(2) The appeal must be started within 20 business (3) Subsection (1)(a) does not apply if the
days (the “submitters appeal period”) after the day approval resulted from a development application
the decision notice or negotiated decision notice is (superseded planning scheme) that was assessed as
given to the submitter. if it were an application under a superseded planning
scheme.
(3) If a person withdraws a submission before the
application is decided, the person may not appeal the (4) Also, a person who has made a request
decision. mentioned in subsection (1) may appeal to the court
against a deemed refusal of the request.
(4) If an application involves both impact
assessment and code assessment, appeal rights for (5) An appeal under subsection (4) may be started
submitters are available only for the part of the at any time after the last day the decision on the
application involving impact assessment. matter should have been made.
(5) If an application is processed under section Division 9 - Appeals to court about other matters
6.1.28(2), appeal rights for submitters for the Appeals for matters arising after approval given
application are available only for the aspects of the (no co-respondents)
development that would have required public
notification under the repealed Act. 4.1.31.(1) A person to whom any of the following
notices have been given may appeal to the court
against the decision in the notice-
(a) a notice giving a decision on a request to change
or cancel a condition of a development approval.
a.
1
Section 3.1.6 (Preliminary approval may override
local planning instrument)
Page 8 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Page 9
2009/1382
(b) a notice under section 6.1.442 giving a decision to (d) the length of a period mentioned in section 3.5.21
change or cancel a condition of a development relevant period;
approval. (e) a deemed refusal.
(2) The appeal must be started within 20 (2) An appeal under subsection (1)(a) to (d) must
business days after the day the notice of the decision be started within 20 business days (the “applicant’s
is given to the person. appeal period”) after the day the decision notice or
(3) Also, a person who has made a request negotiated decision notice is given to the applicant.
mentioned in subsection (1)(a) may appeal to the (3) An appeal under subsection (1)(e) may be
court against a deemed refusal of the request. started at any time after the last day a decision on the
(4) An appeal under subsection (3) may be matter should have been made.
started at any time after the last day the decision on The Registrar for the Building and Development
the matter should have been made. Tribunal may be contacted at the website
Appeals against decisions to change approval http://www.localgovernment.qld.gov.au/
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
For Infrastructure Charges Only
decision made on an application to change the 4.1.36 Appeals about particular infrastructure
conditions attached to an approval given under charges
section 2.19(3)or section 4.4 of the repealed Act may (1) This section applies to a person who has been
appeal to the court against- given, and is dissatisfied with, an infrastructure
(a) the decision; or charges notice or a regulated State infrastructure
(b) a deemed refusal of the application. charges notice.
(2) An appeal under subsection (1)(a) must be (2) The person may appeal to the court against the
started within 20 business days after the day notice of notice.
the decision is to be given to the person. (3) The appeal must be started within 20 business
(3) An appeal under subsection (1)(b) may be days after-
started at any time after the last day a decision on the (a) if the notice is given because of a development
matter should have been made. approval or master plan approval-the day the
Appeals against local laws applicant is given notice of the decision about the
approval; or
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions (b) otherwise-the day the notice is given to the
applied under a local law about the use of premises or person.
the erection of a building or other structure permitted (4) An appeal under this section may only be about-
by the planning scheme may appeal to the court (a) whether a charge in the notice is so
against the decision or the conditions applied. unreasonable that no reasonable relevant local
(2) The appeal must be started within 20 business government, State infrastructure provider or
days after the day notice of the decision is given to the coordinating agency could have imposed it; or
applicant. (b) an error in the calculation of the charge.
For Building Works Only (5) To remove any doubt, it is declared that an
Rights of appeal conferred by Section 4.2.9 of the appeal under this section can not be about the
Integrated Planning Act 1997 as follows: methodology used to establish the charge in the
relevant infrastructure charges schedule or regulated
Division 3 – Appeals to tribunals relating to
State infrastructure charges schedule.
development applications
Appeals by applicants
4.2.9(1) An applicant for a development application
may appeal to the Building and Development Tribunal
against any of the following-
(a) the refusal, or the refusal in part, of a development
application;
(b) a matter stated in a development approval,
including any condition applying to the
development, and the identification of a code
under section 3.1.6;3
(c) the decision to give a preliminary approval when a
development permit was applied for;
a.
2
Section 6.1.44 (Conditions may be changed or
cancelled by assessment manager or concurrence
agency in certain circumstances)
3
Section 3.1.6 (Preliminary approval may override
local planning instrument)
Page 9 of 9
This page was created using easyPDF SDK trial software.
To purchase, go to http://www.bcltechnologies.com/easypdf/
Used in these records
Decision Notice - 010.2009.00001382.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 69 KB (small file)
- File type
No other editions are linked here.