Decision Notice - 010.2009.00001382.001 [As Published] · 142009.1382

of 9

Text shows just the words. Original shows the document exactly as it was published.

                                                                                      2009/1382



3.    The management of roof and surface stormwater runoff shall generally be in accordance with
      Duke Environmental Management Consultant’s “Stormwater Quantity Management Plan”
      AA07731SMP dated Jan 2008.
4.    A Traffic Management Plan (TMP) for the development addressing all construction phases
      shall be prepared by suitably qualified persons and submitted to Council for approval prior to
      the pre start meeting. The TMP shall address, but not be limited to, all items listed below and
      shall be flexible in that it addresses all stages of the development.
      a.    A single nominated access location to and from the site.
      b.    The plan should detail the routing of trucks to and from the site.
      c.    Provision of onsite parking for personnel working on this development, as there is
            limited parking available in adjacent streets.
      d.    Provision of safe cycle and pedestrian movements in the vicinity of the development on
            Elanda Street.
      e.    No queuing of trucks is permitted on residential streets, especially prior to 7.00am.
            Further parked trucks must have engines turned off.
      f.    Provision of signage and traffic controllers in accordance with Manual of Uniform Traffic
            Control Devices and the Transport Infrastructure (Roads) Act.
      g.    Provide an indication where the surplus spoil (if any) is to be transported to, and/or the
            source of any imported fill material.
5.    A 1.5 metre wide concrete footpath shall be constructed across the full frontage of the
      development. The alignment shall be determined on site with Council’s Construction Technical
      Officer. The footpath shall have a slip resistant surface and the expansion joints shall be “saw
      cut”, not trowel jointed.
6.    The total required pavement thickness shall be based on the Department of Main Roads’
      Pavement Design Manual using soaked CBR tests of the subgrade.
      The design pavement thickness, together with CBR test results shall be submitted to Council’s
      Chief Executive Officer (CEO) for approval prior to placement of pavement material.
7.    All landscaping is to be constructed in accordance with Council’s Planning Scheme Policy
      PSP03 Landscaping Plants and Guidelines. Note that the species “Agave attenuate” is not
      approved.
8.    Suitable root barriers shall be installed where proposed trees are adjacent to paths, pavement,
      etc; in accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
      Guidelines.
9.    Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily
      installed into the first existing external downstream stormwater structure.
      These devices are to be checked and cleaned on a regular basis and specifically after each
      rain event.
      These devices are to remain in place during the civil works and construction phases of the
      development.
      The location and type of device to be installed shall be established at the “pre start” meeting
      with Council’s Construction Technical Officer and shall be installed prior to the
      commencement of any works.
10.   Council’s Construction Technical Officer (phone 0410 512 505) shall be given seven (7)
      days’ notice of intention to commence works to arrange a “pre start” meeting prior to
      the commencement of those works.
11.   The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any subcontractors also have the appropriate insurance and public liability documentation.
                                                                                     Page 2 of 9




                    This page was created using easyPDF SDK trial software.
                   To purchase, go to http://www.bcltechnologies.com/easypdf/

Used in these records

About this file

File size
69 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2009.00001382.001 [As Published].pdf · 69 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.