4. Safe Work Method Statement
   Register
The following is a list of Woollam Constructions’ Safe Work Method Statements. A cross in the corresponding
box will indicate it is required on this particular project:

  High Risk Construction Work
                                            Req’d     SWMS                                              Req’d
  SWMS

  Confined Spaces                                     Refuelling Plant and Equipment

  Control of Exposure to RCS                          Traffic Control

  Demolition and Structural Alteration
                                                      Telehandler Operation
  Work

  Elevated Work Platform Operation                    Working at Heights

  Trenching and Excavation                            Working Near Overhead Power Lines

  Forklift Operation                                  Man and Material Hoist Operation

  Hazardous Substance and Dangerous
                                                      General Site Works
  Goods

  Mobile Scaffold                                     General Internal Carpentry

  Working with or Around Mobile Plant                 General External Carpentry

  Precast and Tilt Panel Erection                     General Concrete Works



All Safe Work Method Statements submitted by Contract Partners shall be reviewed by Woollam Constructions
for adequacy and recorded on the online Safe Work Method Statement Checklist. A completed copy of the
Safe Work Method Statement Checklist will be kept electronically as evidence of review.
If there are deficiencies listed on the Safe Work Method Statement Checklist, the Safe Work Method
Statement shall be returned to the Contract Partner, and the Contract Partner shall make the required changes
to the Safe Work Method Statement prior to commencing work.
Any alterations or amendments to a Safe Work Method Statement must be communicated to the relevant
employees by Woollam Constructions or the relevant Contract Partner via a Daily Prestart Meeting and
recorded on the relevant SWMS and Daily Prestart Talk form.
A review of the Contract Partner SWMS shall be facilitated by the Site Manager and or the Site HSE Adviser
with the respective Contract Partner every 3 months, should that Contract Partner still be on the project.
Contract Partner’s SWMS will be filed either in hard copy on site, electronically in the relevant project online
portal or both. In the event of a notifiable incident, then this WHSMP, and any relevant SWMS, will be retained
for a minimum period of two years.




                                                                                   WHS Management Plan / Page 15

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads -.pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.