WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Plans and drawings: the text below has words only, no drawings.
• No illegal substances or alcohol are permitted on the project site.
• Workers will not consume alcohol or drugs during working hours.
• Workers will be fit for work, and if prescription drugs are taken that may affect work safety, the Site
Manager/HSE Adviser must be notified before the start of works.
5.6 Amenities
The following amenities will be provided for all workers:
• Toilets.
• Facilities for washing hands and face.
• Cool, clean drinking water.
• Room or shelter where meals can be taken.
• Toilets must be used – urinating elsewhere is not permitted.
All workers are expected to help maintain the amenities in clean and tidy manner and report to the Site
Manager/HSE Adviser if amenities require maintenance, repairs or moving. Amenities to be maintained to
relevant Australian Standards.
5.7 Plant Operation
• Only ticketed/competent persons shall operate plant on site. Competency needs to be ascertained by
a Registered and qualified RTO.
• Operators of scissor lifts must be in possession of an appropriate qualification i.e. a yellow card to
operate onsite.
• Contract Partners and workers shall supply the Site Manager/compliance officer with copies of
Certificates of Competency or other relevant qualifications before starting work.
• Contract Partners shall supply the Site Manager/compliance officer with evidence that plant brought
onto the site is safe for use before starting work.
• Plant Operators must complete the Mobile Plant Checklist before undertaking any tasks.
• All mobile plant will have roll-over protection, operational warning lights, fire extinguishers and
reversing alarms fitted and working.
5.8 Electrical
• All portable electrical equipment must be tested and tagged three monthly and maintained in a
serviceable condition, this includes all site containers and offices where power is being used.
• Temporary power boards to be fixed securely to the ground or wall at all times.
• Double adapters and/or piggyback adapters of any kind are prohibited.
• Residual Current Devices (RCD) must be fitted to all construction wiring and portable generators.
• Portable generators must have appropriate earthing mechanisms and RCD protection.
• All temporary power boards must be installed by a licensed electrician and comply with the
requirements set out in AS/NZS 3012:2010.
• A register must be kept and maintained on site for all RCD trip tests.
• Electrical leads must be tested, tagged, less than 30 metres and protected from damage and liquids at
all times.
• Wherever practical leads should be elevated off the ground on insulated hooks or lead stands. Never
wrap electrical cables around metal objects.
• Electrical contractors must complete the Electrical Isolation Checklist on Procore prior to any
electrical isolation.
5.9 House Keeping
WHS Management Plan / Page 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.