11. Site Diary
The Site Diary for the project will be undertaken on a cloud-based software system each day by the Site
Manager. The Site Diary will be used to record the following:
• Notes Register – the notes register is to record activities that could include but not be limited to:
- Incidents.
- Hired Plant information.
- Activities and associated hazards on site.
• Weather conditions
• Timecard entry – a record of all Woollam Constructions’ employees worked hours.
• Man Hours Register – a record of all Contract Partner’s worked hours.
All completed Site Diaries will be filed, and can be accessed, through the relevant project and recorded on
Procore.
WHS Management Plan / Page 28
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.