12.Weekly Safety and
Environmental Site Inspection
The Site Inspection for the project will be undertaken on the cloud-based software system, Procore.
Weekly Safety Inspection – undertaken each week by the Site Manager on the inspection’s portal of cloud-
based software system. Using the template refer to each prompt and mark pass, fail or N/A. An observation
will be created for any follow up actions required. Observations will be documented including a description of
what action is required, who is to complete the action and when it must be completed. Once observations
have been rectified to an approved and satisfactory standard that they should be closed out.
All completed Weekly Safety and Environmental Inspections will be filed, and can be accessed, through the
relevant project online portal.
Weekly Safety and Environmental Inspections to be completed in line with Procore Inspection Matrix.
As found in Procore -
WHS Management Plan / Page 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHS Management Plan Ozcare Noosa RACF WC OHS 002 Rev 23 4 July 2023 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.