73. Sediment and erosion control measures must be placed on site prior to the works commencing and shall
be maintained until all works are complete. The erosion and sediment control measures shall be in
accordance with the “Best practice guidelines for control of stormwater on building sites” prepared by
Healthy Waterways (copy attached or available at www.healthywaterways.org).
74. All disturbed areas must be revegetated or otherwise stabilised at the completion of the works. Disturbed
areas are revegetated using species identified in PSP3 – Landscaping Plants and Guidelines.
75. The transportation of all materials to and from the site must be undertaken in a manner such that no
particle matter escapes onto a public road. All vehicles carrying out materials either to or from the site
shall be covered to prevent materials including dust being windblown from the vehicle.
76. A Waste Management Plan shall be submitted for the demolition to the Land Use Section of Noosa
Council, prior to the development permit for building works being issued. The Plan shall contain the
following information:-
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated volume (m³) On-site *specify Off-site *specify *Specify contractor
materials proposed reuse or contractor & & landfill site
onsite recycling recycling outlet
methods
Excavation material
Green waste
Bricks
Concrete
Timber – please
specify
Plasterboard
Metals – please
specify
Asbestos
Other – please
specify
Note * Details of site area to be used for onsite separation, treatment and storage (including weather
protection) shall be provided on the plan drawings accompanying your application. If a demolition
contractor is undertaking works, then the Waste Management table is to be completed by the demolition
contractor.
The purpose of the Waste Management Plan is to facilitate the segregation of waste for the effective
reuse and recycling of such materials. Additionally Council rewards those who segregate waste by
significantly reducing disposal fees at the landfill some items are free. Higher gate fees are charged for
loads of mixed waste.
Environmental Health
77. The developer must provide waste storage and disposal facilities in accordance with Planning Scheme
Policy No 9 “Waste Management Multi-Dwellings and Commercial and Industrial Premises”, including an
external imperviously paved area correctly sized for all refuse and recycling containers and suitably
screened from public places and neighbouring properties. A roofed waste/bin wash area is required with
a cold-water tap, hose and drain outlet connected to sewer, via a bucket trap and grease arrestor.
78. Noise emission from mechanical equipment (air conditioners, refrigeration equipment or pool pumps etc)
shall comply with the following requirements:
The equipment shall be installed and located in a manner that prevents excessive noise in accordance
with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-the-spot fines) may
apply for offences.
A person must not use equipment on any day if it makes or causes noise to be made –
From 10pm to 7am: More than the lower of either –
40 dB(A)
3 dB(A) above the background noise level
No audible noise for pool pumps apply during these hours.
From 7am to 7pm: More than the lower of either –
50 dB(A)
5 dB(A) above the background noise level
MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@ec1203b7\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Negotiated Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 156 KB (small file)
- File type
No other editions are linked here.