SUPERSEDED Negotiated Decision Notice [As Published] · 132007.1181

of 16

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                  8 of 16


       59.3. Indicate the location of any “holding” areas for heavy vehicles and

       59.4. Operating hours.

60.    A Condition Survey should be carried out on adjoining buildings, structures and services prior to any
       excavation or construction works taking place on site. If distress already exists, a photographic survey
       should be undertaken, the distress measured and a plan to monitor changes to distress shall be
       implemented.
Erosion and Sediment Control
61.    Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
       control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
       waste, will be necessary.
     In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
     to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
62.    A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
       specifications for all engineering works that will become Council infrastructure, which shall be submitted in
       conjunction with an application for a Development Permit for Operational Works. To avoid conflict with
       underground pipes or services, all existing and proposed services required by the development shall be
       shown on the plans.

63.    Any alteration of any public utility or other facilities necessitated by the development of the land or
       associated construction works external to the site shall be at no cost to Council.

64.    The transportation of all materials to and from the site shall be undertaken in a manner such that no
       particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
       be covered to prevent materials including dust being windblown from the vehicle.
Building Services
65.    The works must be undertaken in a manner that causes no detrimental effect upon the amenity of the
       neighbourhood by reason of the creation of excessive noise, lighting, air-borne hazards, atmospheric
       pollutants (including dust or odours) nuisance or any other emissions in accordance with the nuisance
       provisions of the Environmental Protection Regulation 1998 or Council’s Local Law No. 12 – Control of
       Nuisances.

66.    Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
       damage and made safe to the standard required by the regulatory authority;

67.    All infrastructure must be disconnected, capped or sealed including:-
              electricity meters removed and electrical wires disconnected; and

              telephone lines are disconnected; and

              high speed data cables and television provider boxes are disconnected and removed to the
              standard required by the regulatory authority;


68.    All building materials containing asbestos, including asbestos cement sheeting or roofing and lagging,
       must be removed from the building and disposed of in accordance with industry best practice.

69.    Waste generated during construction must be stockpiled in a centralised location and covered as required
       to prevent material being blown onto adjoining properties including the road reserve or food waste from
       generating vermin. All site waste must be disposed of to an approved waste disposal facility either directly
       or via an approved waste receptacle and collection service. Storage areas are to be located near the
       temporary access to the site so that access can be gained with out damage to infrastructure.

70.    All building materials containing asbestos products must be disposed on in accordance with industry best
       practice.

71.    A temporary crossing must be provided to protect road reserve infrastructure including kerb and channel;

72.    Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site, the
       relocation site or between the sites must be repaired or reinstated to at least pre-existing conditions.




MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@ec1203b7\@[email protected]

Used in these records

About this file

File size
156 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Negotiated Decision Notice [As Published].pdf · 156 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.