Original source · versioned page text
SafeWorkMethodStatement QLD Demolition
Safe Work Method Statement – 16-120 POINCIANA AVE, TEWANTIN QLD 4565
Revision No: 1 Date Printed: Page 13
KHODR CIVIL PTY LTD Initial: 19/02/2025
The following personnel have responsibility of the work and the inspection and approval of the work areas, work methods, protective
measures, plant equipment and power tools.
Name Position Signature Company
Site Manager KHODR CIVIL PTY LTD
Permits Required: Yes No Yes No Yes No
Daily SWMS Physical Isolation (Gas, Water, Sewer) Electrical Isolation
Confined Spaces
Additional Heath & Safety Precautions
Training Required Yes No Yes No Yes No Yes No
Construction Industry Induction Site Induction Tool Box Meetings Task Specific
(Green Card)
Manual Handling PPE Noise Confined Space
Other