Minor Change Existing Approval - 152000.200053.3 (As Published)

of 12

Text shows just the words. Original shows the document exactly as it was published.

               41.    To protect the environment against siltation/sediment export or soil erosion as a result of this
                      development, an erosion and sediment control plan must be submitted in conjunction with
                      any Development Permit for Operational Works. Site control measures such as silt fencing,
                      controlled gravel access to the site and controlled disposal of waste, may be necessary.
                      All physical site control measures shall be installed, and maintained in working order at all
                      times until all operational works have been completed and accepted on maintenance. The
                      erosion and sediment control plan must be adhered to at all times.
               42.    A reticulated water supply system shall be provided to connect to Council’s existing systems,
                      including a metered water connection to the property boundary of each proposed new lot
                      within the site.
               43.    Provision shall to be made in all parks locations for a water connection. Under-road service
                      conduits shall be provided to ensure a connection is available.
               44.    Fire hydrants are to be provided throughout the development in accordance with Noosa
                      Council and Queensland Fire Service standards.
               45.    All connections to the sewer system shall be carried out either by Council or by a Council
                      approved Contractor, at no cost to Council. Any connection to a water main shall be
                      undertaken by Council.
               46.    Conduits and kerb markers shall be installed for all necessary service crossings of roads to
                      Council's satisfaction. An "As Constructed" plan showing the locations of the conduits shall
                      be submitted to Council prior to acceptance of the works "On Maintenance".
               47.    The requirements of ENERGEX, OPTUS and/or TELSTRA shall be satisfied in relation to
                      any existing services that currently traverse the site. Written confirmation by the relevant
                      authorities that satisfactory arrangements have been made to formalise any existing informal
                      services shall be submitted prior to Council endorsing the Plan of Survey.
               48.    An underground electricity service shall be provided to each lot. Full details of the proposal
                      forwarded to ENERGEX for its approval shall be submitted to Council.
                      The approval of ENERGEX and a “Certificate for Electricity Supply to Subdividers” will be
                      required to be submitted by Council prior to endorsing the Plan of Survey.
                      Any agreement with ENERGEX shall be wholly at the applicant's expense, and shall not
                      entail a financial encumbrance on future purchasers of the proposed lots.
                      Street lighting is to be provided throughout the subdivision in accordance with Council
                      Standards.
                      The design is to be carried out by an Electrical Design Consultant approved by ENERGEX.
                      The consultant shall liaise with Council’s Manager - Works Support during preparation of the
                      design.
               49.    All stormwater drainage shall be designed in accordance with the provisions of the 1987
                      Australian Rainfall and Runoff (A.R.R.), Australian Standard AS3500.3.2-1998 ‘Stormwater
                      Drainage-Acceptable Solutions’ and Noosa Council Standards. Pipe and channel drainage
                      systems shall be designed to cater for:-
                      49.1. Ten (10) year Average Recurrence Interval design storm (ARI) in the case of low or
                            medium residential developments and local roads.
                      49.2. Twenty (20) year ARI. in the case of high density residential development, commercial
                            or industrial developments and collector roads.
                      49.3. In all cases the major event surface flow paths shall be designed to cater for the one
                            hundred (100) year ARI.




                                                                                                       Page 8 of 12
Document Set ID: 25217809
Version: 7, Version Date: 07/10/2026

Used in these records

About this file

File size
192 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - 152000.200053.3 (As Published).pdf · 192 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.