Approved Decision Notice - MCU24 0089 & OPW24 0099 [As Published] · MCU24/0089

of 14

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                             Officer:            Mark Lewis
                                                             Direct Telephone:   07 53296290
                                                             Our Reference:      MCU24/0089 & OPW24/0099
                                                             Your Reference:     .

               16 October 2024


               Pontoon Works
               121 Esplanade
               GOLDEN BEACH QLD 4551
               [email protected]



               Dear Sir/Madam,
                                                         Decision Notice
                                                         Planning Act 2016

               I refer to your application and advise that on 10 October 2024, Council decided to approve the
               application, subject to conditions.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              MCU24/0089 & OPW24/0099

                   Street address:              33 Wyuna Dr Noosaville Qld 4566

                   Real property description:   Lot 16 N 10576

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Material Change of Use - Landing – Residential, and
               •       Development Permit for Operational Works – Prescribed Tidal Works - Jetty
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

                       Approved Plans
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.




               ABN 97.969.214.121                                                                    PO Box 141
               noosa.qld.gov.au                                                               Tewantin QLD 4565
               [email protected]                                                               07 5329 6500
                                                                                                           Page 1 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024
Full text of the other 13 pages

Page 2

                         Plan No.           Rev.   Plan/Document Name                        Date

                         24.002             F      Site Plan prepared by Kunkel Building 27 August 2024
                                                   Design
                         Sheet 1 of 2

                         24.002             F      Floor Plan, Floor Framing Plan & 27 August 2024
                                                   Typical Section prepared by Kunkel
                         Sheet 2 of 2
                                                   Building Design

                         S01                A      General Notes prepared by HR Design       3 April 2024

                         S02                A      Bearer & Joists Layout prepared by HR 3 April 2024
                                                   Design

                         S03                A      Connection Details prepared by HR 3 April 2024
                                                   Design

                      Currency Period
               2.     The Currency Period for this development approval lapses if all conditions have not been
                      complied with, and the plan of survey lodged with Council for endorsement by 10 October
                      2026, unless an application to extend the currency period is approved by Council.
                      Performance Bond
               3.     Security in the form of a cash bond or trading bank guarantee to the sum of $2000 must be
                      submitted to Council, to secure performance of all conditions of this approval, prior to the
                      commencement of the works. The cash bond or trading bank guarantee will be returned on
                      performance of the conditions of this approval less any costs incurred by Council in respect
                      of enforcing performance of this permit. Council reserves the right to call upon the bond or
                      guaranteed sum to effect compliance with conditions.
                      General Conditions
               4.     The approved use is for one (1) Landing as defined by the Noosa Plan 2020 and is to be
                      used for private purposes only with no commercial operations to be undertaken.
               5.     The existing Landing (pontoon and gangway) is to be decommissioned and wholly removed
                      prior to the commencement of the use.
               6.     The maximum number of vessels that may be berthed, moored, attached or stored on the
                      structure must not exceed 2.
               7.     The use of the landing must not cause any adverse effects on the amenity of the surrounding
                      areas including changes to light, views, air quality and noise.
               8.     Vessels berthed/moored at the Landing must be located a minimum of 3.0 metres from the
                      prolongation of the property boundaries, and clear of the fish habitat area.
               9.     Vessels must be connected directly to the Landing, and not located side by side or in tandem
                      with another vessel.
               10.    All structures must be designed and constructed such that they are free standing within the
                      waterway and are not connected to or behind the revetment wall
               11.    All structures must have no detrimental effects on stormwater drains and/or easements.
               12.    Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the top of the
                      revetment wall.
               13.    A rigid handrail must be fitted on one side of the walkway. The handrail must be of an open
                      design and in accordance with the approved plans.




                                                                                                    Page 2 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Page 3

               14.    No posts or vertical supports of the proposed jetty are to extend vertically from the structure
                      unless they provide necessary support for the handrail.
               15.    No boatlifting devices are to be attached or moored at the jetty structure for the purpose of
                      elevating a vessel above the water without Council approval.
               16.    There must be no electrical reticulation system carrying electricity in excess of 24 volts
                      beyond the revetment wall unless all switches and power outlets are positioned above the
                      1%AEP flood level.
               17.    Lighting associated with the use must be designed, installed, operated, and maintained in
                      accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
               18.    The jetty is to be used for private purposes only with no commercial operations to be
                      undertaken.
               19.    Boat repair activities are not permitted on site.
               20.    Wastewater and sullage must only be disposed of at approved pumpout facilities.
               21.    The mooring facility must not be utilised for live-aboard purposes.
               22.    Any construction and post construction activity is not to impact on the condition of the
                      waterway, and is to be conducted so as not to breach the Environmental Protection Act EPA
                      (1994) and the Environmental Protection (Water) Policy 2009.
               23.    Certification by a Registered Professional Engineer of Queensland that states that the jetty
                      is constructed in accordance with best practice methods and is structurally sound must be
                      submitted to Council. This certification must be submitted to Council within three (3) months
                      of the completion of the works. A final inspection and approval of the structure by Council’s
                      Inspector is also required. Please contact Council’s Development Assessment Branch on
                      5329 6500 to arrange the inspection.
               24.    This approval lapses where the construction of the jetty has not commenced within two (2)
                      years of the date of issue of the approval, unless application is made and approved by
                      Council for an extension.
               25.    After completion, the proposed works must be maintained in a sound state of repair in
                      accordance with the approved plans.
               5.     REFERRAL AGENCIES

               The referral agencies applicable to this application are:

                Referral Status        Referral Agency and Referral Trigger                 Response
                                       Address

                Concurrence            SARA at DILGP SARA        Schedule 10, Part 17,      The agency provided its
                                       at DILGP Via MyDAS2       Division 1 – Tidal Works   response on 12
                                       at https://prod2.dev-     or                         September 2024
                                       assess.qld.gov.au/suite                              (Reference No. 2407-
                                                                 work in a Coastal
                                       / (for assistance,                                   41532 SRA). A copy of
                                       contact DILGP at 5352     Management District        the response is
                                       9701 or                                              attached
                                       email:[email protected]




                                                                                                       Page 3 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Page 4

               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     This approval does not capture any proposed additions or alternations to the existing dwelling
                      or within the rear boundary setback. Any proposed additions and alternations are subject to
                      the Accepted Development provisions of the Noosa Plan 2020.
               2.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects
                      of the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               3.     The approval or conditions do not absolve the owner of the land from complying with all the
                      conditions of this approval and/or relevant Council By-Laws and Policies and/or relevant
                      statues and/or statutory regulations in the execution and/or performance of said works.
               4.     An applicant for a development application may make an agreement with an assessment
                      manager, referral agency or other person to establish the responsibilities, or secure the
                      performance, of a party to the agreement about a development condition.
               5.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               6.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Building and Construction Industry (Portable Long Service Leave) Levy
               7.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
               7.     PROPERTY NOTES

               Not applicable.
               8.     VARIATION APPROVAL DETAILS

               Not applicable.
               9.     FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               10.    SUBMISSIONS

               Not applicable.
               11.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.




                                                                                                       Page 4 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Page 5

               12.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Mark Lewis
               Coordinator - Engineering



               Enc:   Appeal Rights
                      Referral Agency Response
                      Approved Plans/Documents

               cc.    SARA at DILGP
                      Via MyDAS2 at https://prod2.dev-assess.qld.gov.au/suite/
                      (for assistance, contact DILGP at 5352 9701 or email [email protected])




                                                                                                            Page 5 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Page 6

                                       Referral Agency Response
                                       PLANNING ACT 2016 & PLANNING REGULATION 2017




                                                                                      Page 6 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Page 7

 

Document Set ID: 23303042

2407-41532 SRA

SARA trigger: Schedule 10, Part 17. Division 3, Subdivision 1, Table 1 (Planning
Regulation 2017) — Tidal works or work in a coastal management
district

Schedule 10, Part 17, Division 3, Subdivision 2, Table 1 (Planning
Regulation 2017) — Tidal works or work in a coastal management

district
SARA reference: 2407-41532 SRA
Assessment manager: Noosa Shire Council
Street address: 33 Wyuna Drive, Noosaville
Real property description: Lot 16 on N10576
Applicant name: Pontoon Works
Applicant contact details: Mr Lindsay Parker
4/1 Bronwyn Street
Caloundra West QLD 4551
[email protected]
Human Rights Act 2019 A-consideration of the 23 fundamental human rights protected under
considerations: the Human Rights Act 2019 has been undertaken as part of this
decision. It has been determined that this decision does not limit
human rights.

Representations

 

An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment
Rules). Copies of the relevant provisions are in Attachment 4.

A copy of this response has been sent to the applicant for their information.

For further information please contact Celeste Bownds, Senior Planning Officer, on 07 5352 9708 or via
email [email protected] who will be pleased to assist.

Yours sincerely

i ( }
Jamaica Hewston
Acting Manager
cc Mr Lindsay Parker, [email protected]
enc Attachment 1 - Referral agency conditions
Attachment 2 - Advice to the applicant
Attachment 3 - Reasons for referral agency response

Attachment 4 - Representations about a referral agency response provisions
Attachment 5 - Documents referenced in conditions

State Assessment and Referral Agency Page 2 of 7

Version: 2, Version Date: 16/10/2024

 

Page 7 of 14

Page 8

 

 

Document Set ID: 23303042

2407-41532 SRA

Attachment 1—Referral agency conditions

 

(Under section 56(1)(b)(1) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)

 

No. | Conditions Condition timing

 

Operational work — prescribed tidal works (jetty)

 

Schedule 10, Part 17, Division 3, Subdivision 1, Table 1 (Planning Regulation 2017) — Tidal works or
work in a coastal management district—The chief executive administering the Planning Act 2016
nominates the Director-General of the Department of Environment, Science and Innovation to be the
enforcement authority for the development to which this development approval relates for the
administration and enforcement of any matter relating to the following conditions:

 

 

 

1. The development must be carried out generally in accordance with For the duration of
the following plan: works and to be
* Site Plan, prepared by Kunkel Building Design, dated maintained
27/08/24, sheet number 01 and revision F.
2. The works to which this approval relates are to be for a private At all times
purpose only.
3. Any operator and contractor involved in the works to which this During construction

approval relates must:

(a) be provided a copy of these referral agency conditions

(b) install all measures, plant and equipment necessary to
ensure compliance with the conditions of this approval

(c) maintain such measures, plant and equipment in a proper
and efficient condition; and

(d) operate such measures, plant and equipment in a proper
and efficient manner.

 

4. For the jetty works only use materials which are free from During construction
contaminants as defined under section 11 of the Environmental
Protection Act 1994.

 

5. Should the works become damaged as a result of erosion, flooding At all times
or storm tide inundation, the registered landowner/s of the subject
land shall be responsible for the removal of alll debris at their own
expense.

Schedule 10, Part 17, Division 3, Subdivision 2, Table 1 (Planning Regulation 2017) — Tidal works or
work in a coastal management district—The chief executive administering the Planning Act 2016
nominates the Director-General of the Department of Transport and Main Roads to be the enforcement
authority for the development to which this development approval relates for the administration and
enforcement of any matter relating to the following conditions:

6. The development must be carried out generally in accordance with At all times

the following plan:

* Site Plan, prepared by Kunkel Building Design. dated
27/08/24, sheet number 01 and revision F.

 

 

 

 

 

7. (8) Light/mark all vessels, structures, plant and equipment For the duration of
associated with: works and for operation
i. the works, in accordance with the following specifications: to be maintained at all
® any anchors deployed must be marked with yellow times

buoys and fitted with FL yellow lights fitted

 

 

 

 

 

State Assessment and Referral Agency Page 3 of 7

Version: 2, Version Date: 16/10/2024

 

Page 8 of 14

Page 9

 

2407-41532 SRA

 

® lighting provided must not obscure, disguise or
otherwise interfere with the effectiveness of
navigational lighting.
ii. operations, in accordance with the following specifications:
* section 3 of AS4282-1997 Control of the obtrusive
effects of outdoor lighting
* pedestrian style lighting to deck or retro reflective tape
on outer deck piles.
Lighting provided must not obscure, disguise or otherwise interfere
with the safe navigation of other vessels, including the effectiveness
of navigational lighting.

 

The construction, operation and maintenance of the jetty and any
ship berthed, moored or attached to the structure, must not:
(a) encroach into, pass over or under a navigation corridor
(b) be located in a high-risk maritime zone
(c) impede the safe navigation of other ships or boats
(d) restrict safe access to or from neighbouring structures.

For the duration of
works, and at all times

 

 

 

(a) Remove and dispose of any debris or similar obstruction
encountered whilst undertaking the work at an appropriately
licensed facility.

(b) All structures to be demolished, both above and below the
waterline must be:

i. completely extracted: or
ii. cut-off below bed level.

(c) Submit written confirmation to [email protected] or

mailed to:

Maritime Safety Queensland
PO Box 1094
Mooloolaba QLD 4557

confirming that the structures have been demolished in
‘accordance with part (b) of this condition.

The written confirmation must state 2407-41532 SRA, the
location and the name of the registered place and the condition
number under which the confirmation is being given.

 

(a) and (b) For the
duration of works

(c) Within 5 business
days of the completion
of works

 

 

 

State Assessment and Referral Agency

Page 4 of 7

 

 

Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Page 9 of 14

Page 10

 

2407-41532 SRA

Attachment 2—Advice to the applicant

 

 

General advice

1. Terms and phrases used in this document are defined in the Planning Act 2016, its regulation
or the State Development Assessment Provisions (SDAP) version 3.0. If a word remains
undefined it has its ordinary meaning.

 

 

 

 

 

State Assessment and Referral Agency Page 5 of 7

Document Set ID: 23303042 Page 10 of 14

Version: 2, Version Date: 16/10/2024

Page 11

 

 

2407-41532 SRA

Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)

 

The reasons for SARA's decision are:
* The proposed development has been assessed against and complies with State code 7: Maritime
Safety of the SDAP version 3.0, with conditions. In particular, the development:
© does not compromise the viable operation of aids to navigation
© does not compromise the safe operation of vessels in navigable waterways.
* The proposed development has been assessed against and complies with State code 8: Coastal
development and tidal works of the SDAP version 3.0, with conditions. In particular, the development:
maintain coastal processes
conserve coastal resources
maintain appropriate public use of, and access to and along, State coastal land
does not result in @ significant residual impact on a matter of state environmental
significance.

oooo

Material used in the assessment of the application:

the development application material and submitted plans

Planning Act 2016

Planning Regulation 2017

the State Development Assessment Provisions version 3.0, as published by SARA
the Development Assessment Rules

SARA DA Mapping system

section 58 of the Human Rights Act 2019

Attachment 4—Representations about a referral agency response
provisions

 

(page left intentionaily blank)

State Assessment and Referral Agency Page 6 of 7

 

Document Set ID: 23303042 Page 11 of 14

Version: 2, Version Date: 16/10/2024

Page 12

 

2407-41532 SRA

Attachment 5—Documents referenced in conditions

 

(page left intentionally blank)

State Assessment and Referral Agency Page 7 of 7

 

 

Document Set ID: 23303042 Page 12 of 14

Version: 2, Version Date: 16/10/2024

Page 13

 

joundm
wi

pet

aAup
DLR eae

 

 

 

<UNKEL

 
 

 

 

 

SSPIAGGIA INVEST PL, VISTA BLU iL,
TROPICALE INVEST PIL & PARADISO INVEST i

 

ew Jerry

 

 

 

PLANS AND D¢
referred to in the Ri
ENCY RESPOI

 
    

SARAref: 207-4

  

Date

 

 

 

 

 

 

 

 

 

 

signatures

 

lowneris

 

patiaer

 

 

 

 

Document Set ID: 23303042

Version: 2, Version Date: 16/10/2024

Page 13 of 14

 

 

Page 14

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 14 of 14
Document Set ID: 23303042
Version: 2, Version Date: 16/10/2024

Used in these records

About this file

File size
885 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Decision Notice - MCU24 0089 & OPW24 0099 [As Published].pdf · 885 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗