MCU10/2083 Information Request Response 37 Gibson Rd Noosaville

of 89

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.5 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

                                                                                                               e'411




      The bio-retention system is depressed by 250mm below the proposed car park level to provide the required
      extended detention depth. We believe that the change in level will discourage pedestrians from adopting a
      shortcut route through this area. The exclusion of shade trees from the bio-retention system will also provide
      a potential passage for pedestrians, especially as these trees are located between parking bays. The central
      bio-retention basin trench filter material area shown on JFP Sketch Drawing M2383 SW.1 Revision E scales at
      33.34 m2 which is 3.34 m2 greater than the required area of 30 m2. The additional 3.34 m2 can be used as
      formalised pathways/steppingstones (if required) without compromising the function of the bio-retention
      system.


      JFP Sketch Drawing M2383 SW.1 Revision F clearly demonstrates that the required bio-retention filter media
      area footprint is available on site. All the proposed bio-retention systems have vertical (retaining) walls, which
      have been included on the attached revised drawing.

Please contact the undersigned if you wish to discuss any issues pertaining to this matter.




Yours Faithfully,




ANDREW FRASER
Manager - Engineering
JF&P Consulting Engineers Pty Ltd


cc:        Ben Schodel - Blades Project Services

Encl:     JFP Site Based Stormwater Management Plan Revision E




JFP Ref: M2383-001                                                                                                  Page 2
Log in to download the original file

MCU10_2083 Information Request Response 37 Gibson Rd Noosaville.pdf · 15.5 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.