Table 8 - Construction Phase Performance Criteria
Pollutant Potential Source
Total Suspended Solids 90th Percentile < SOmg/L
pH 6.5-9.0
Dissolved Oxygen 901h Percentile > 80% saturation or 6mg/L
Hydrocarbons No visible sheen on receiving waters
Litter No visible litter washed from site
4.4 MONITORING AND MAINTENANCE
The general requirement of monitoring during the construction phase will be:
n Work activities are restricted to designated construction areas
n Earthworks and site clearing are undertaken in accordance with the Erosion and Sediment Control Plans
n Erosion and sediment control devices are to be constructed/installed in accordance with the Erosion and
Sediment Control Plans
• Inspection of sediment fences and erosion and sediment control structures/devices on a weekly basis as
well as after any rain event exceeding 25mm in 24hrs
n Stormwater discharges from the site are not having any adverse affect on the downstream environment
n Monitoring and recording of the performance of the drainage control devices including water quality
testing where required
n Any failure in the stormwater system shall be immediately rectified to prevent uncontrolled discharge
from the site
• Any failure to the stormwater system causing damage to surroundings should implement immediate
remedial work to the damaged area
4.5 RESPONSIBILITY AND REPORTING
n The contractor shall be responsible for monitoring the performance of all drainage control and erosion
and sediment control devices
n Records of any failures to devices should be kept and reported to the Construction Manager
n Regular inspections of the devices shall be reported to the Construction Manager
• Inspections of the devices after heavy rainfall shall be reported to the Construction Manager
SITE BASED STORMWATFR MANAGFMI NT PLAN - Revision E Gibson Rood, Noon 1 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.