4.2 Operational Phase
During the operational stage of the development, the following impacts have been identified in relation to stormwater
runoff and water quality of the receiving waterways:
Potential exists for gross pollutants which include human derived litter, course sediment and vegetation affecting
the drainage capacity of stormwater systems. Gross pollutants are also typically unsightly reducing the visual
amenity of the site. Gross pollutants can also physically affect the downstream waterway habitats and
organisms such as entangling birds and marine animals in plastic;
Sediment and Suspended Solids can become mobilised by stormwater as suspended solids from the erosion of
exposed soil areas, un-mulched garden beds and sediment deposited on car park and hardstand areas by
vehicles and by atmospheric deposition of sediment. Sediment can affect receiving waterways physically
through smothering aquatic flora and fauna. Sediments can also block stormwater systems leading to local
flooding. Suspended solids may also be used as a transport medium for nutrients and heavy metals making
their way into waterways; and
Nutrients can enter the waterways from stormwater runoff through many sources including, detergents used in
car washing, fertilizers from landscaping and lawn areas, nitrous oxide deposition from vehicle exhausts, and
organic waste. Large nutrient levels can lead to eutrophication of the receiving waterways resulting in algal
blooms and excessive macrophyte growth.
Implementation of the appropriate SQID’s would ensure that stormwater leaving the developed site shall be
acceptable to Healthy Waterways, Water Sensitive Urban Design Guidelines for South East Queensland’s
requirements.
4.3 Selection of Storm water Management Options
The Performance Criteria required to be met for discharges from development sites during the ’operational’ (post-
construction) phase of the development is detailed in Table 2.2 of the Urban Stormwater Quality Planning Guidelines
2010.
The load-reduction targets that must be achieved when assessing the post-developed sites treatment train,
(comparison of unmitigated developed case versus developed mitigated case) are listed in Table 2.
Table 2: Storm water Quality Objectives for the Site. (Operational Stage)
Pollutant Issues Load Reduction Objectives (%)
Total Suspended Solids 80
Total Phosphorus 60
Total Nitrogen 45
Total Gross Pollutants 90
Page 19
Level 2, 39 Sherwood Road [email protected] P: 07 3870 8888
Toowong QLD 4066 www.icubed.com.au F: 07 3870 8988
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application part 7 of 10 Stormwater Management Report - MCU13/0092Related documentApplication case desk ↗
About this file
- File size
- 60.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.