Development Application part 7 of 10 Stormwater Management Report - MCU13/0092

of 119

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (60.2 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

                                                                                         i(l.~b   <l   ((>Il$uttiIl9
                                                                                         innovation ingenuity Inspiration
                                                                                                                            11
                                                                                                   ABN 89 106 675 1S6       ..:J)
4.      Water Quality

4.1 Construction Phase


Potential exists during the construction phase for sediment to become mobilised by stormwater as suspended solids
from the erosion of exposed soil areas and stockpiles, and as a result of spillages from construction and plant
operations.

Stormwater quality during the construction phase of the development should be addressed in an Erosion and
Sediment Control Plan. The plan should address construction phase erosion and sediment control issues in
accordance with the Institute of Engineers Australia (Qld)Erosion and Sediment Control Guidelines. The Erosion and
Sediment Control Plan should also be in accordance with the Water Sensitive Urban Design Guidelines for South
East Queensland.


The following measures should generally be implemented prior to the commencement of construction:


     Education of all site workers in sediment and erosion procedures;
     Specified storage areas for construction materials and plant that are bunded to prevent any spillages from
     escaping; and
     Construction of silt fences and catch drains adjacent to the downstream boundaries to divert runoff to temporary
     sediment basins.


The following measures should be implemented during the construction phase of the project:


     Temporary sedimentation basins should be constructed in accordance with Council’s requirements;
     Silt fences should be erected downstream of all disturbed areas; and
     All erosion and sediment control devices should be regularly inspected and maintained following storm events.




                                                      PagelB

Level 2, 39 Sherwood Road                     [email protected]                                  P: 0738708888
Toowong QLD 4066                              www.icubed.com.au                                   F: 07 3870 8988

Used in these records

About this file

File size
60.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Application part 7 of 10 Stormwater Management Report - MCU13_0092.pdf · 60.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.