SPA Decision Notice - 010.2010.00000811.001 [As Published] · 132010.811

of 16

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                             2010/811



Erosion and Sediment Control
37.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to be
      submitted to the Council for approval prior to obtaining a Development Permit for Operational
      Works.
General Engineering Requirements
38.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be
      submitted in conjunction with an application for a Development Permit for Operational Works.
      In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
      submitted in conjunction with any application for Operational Works.
39.   Digital detailed designs including drawings, calculations, specifications and a schedule of works
      shall be submitted with any application for a Development Permit for Operational Works in
      respect of roadworks and stormwater drainage works. The design shall be in accordance with
      Council’s Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage
      and Earthworks. To avoid conflict with underground pipes or services, all existing and proposed
      services required by the development shall be shown on the plans.
40.   To facilitate production of As Constructed drawings it is suggested that all design drawings are
      submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
      use of ADAC are available at www.adac.com.au).
41.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
42.   Any alteration of any public utility or other facilities necessitated by the development of the land
      or associated construction works external to the site shall be at no cost to Council.
43.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
44.   As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
      for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
      type of all services and structures. All of which shall be submitted to Council for checking and
      for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage
      structures, finished ground levels and pavement surface levels. The data shall be submitted in
      the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
      are available at www.adac.com.au). Approval of works shall not be granted until all As
      Constructed information has been supplied and accepted by Council.
Unity Water
45.   Reticulated water supply and sewerage must be provided to the development.
46.   Separate 25mm PE water services must be installed to a common lot boundary with
      independent meters installed outside the boundary of the lot in accordance with Sunshine Coast
      water standard drawing SCW 361. Meters must be “Elster” PSM 50100/39 (dual check).
47.   The sewer inspection opening must be located a minimum of 1.0 metre from any structure and
      be raised to the finished surface level of the site.
48.   Storm water retention systems and gross pollutant traps must maintain a minimum clearance of
      1.5 metres from Council water supply and sewerage infrastructure .
49.   Landscape planting within 1.5 metres of Council sewerage infrastructure must be Council
      approved varieties and low growing when mature.
                                                                                            Page 7 of 16

Used in these records

About this file

File size
293 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SPA Decision Notice - 010.2010.00000811.001 [As Published].pdf · 293 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.