Appendix D- Stormwater Management Plan · MCU23/0078

of 74

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (18.3 MB): may take a few minutes to open.

Log in to see the plans as drawn

Original PDF page 12, section 1. The text section number identifies this passage in the reader.

                    Table 5: Comparison of Rational Method & XP Storm Existing Peak Flows – Site A (m3/sec)
                            AEP (%)     ARI (Years)    Rational Method Result     XP Storm Result
                              63.21              1                    0.286                       0.134
                              39.35              2                    0.344                       0.197
                              18.13              5                    0.520                       0.431
                                10               10                   0.641                       0.613
                                5                20                   0.765                       0.813
                                2                50                   0.968                       0.998
                                1                100                  1.111                       1.182

        As indicated, the XP Storm peak discharge results are of the same magnitude as the results initially estimated using the
        Rational Method. It was therefore concluded that the existing XP Storm model was functioning correctly.


4.1.4   Developed Scenario Model


        A developed scenario model was then created with internal catchments and parameters modified from the existing model
        to suit the proposed development as outline in Table 6, 7 and 8.


                                        Table 6: XP Storm Developed Model Parameters – Site A
                                         Parameter                    Site A Catchment
                                                                Pervious Data       Impervious Data
                                 Area (ha)                            -                    3.46
                                 Slope (%)                            -                     1
                                 Mannings ‘n’                         -                   0.015
                                 Initial Loss (mm)                    -                     0
                                 Continuing Loss (mm/hr)              -                     0
                                 Laurenson ‘n’                      -0.285                -0.285


                                     Table 7: XP Storm Developed Model Parameters – Site B (North)
                                          Parameter               Site B Northern Catchment
                                                                Pervious Data       Impervious Data
                                 Area (ha)                            -                    0.25
                                 Slope (%)                            -                     1
                                 Mannings ‘n’                         -                   0.015
                                 Initial Loss (mm)                    -                     0
                                 Continuing Loss (mm/hr)              -                     0
                                 Laurenson ‘n’                      -0.285                -0.285


                                     Table 8: XP Storm Developed Model Parameters – Site B (South)
                                          Parameter               Site B Southern Catchment
                                                                Pervious Data       Impervious Data
                                 Area (ha)                            -                    0.45
                                 Slope (%)                            -                    1.5
                                 Mannings ‘n’                         -                   0.015
                                 Initial Loss (mm)                    -                     0
                                 Continuing Loss (mm/hr)              -                     0
                                 Laurenson ‘n’                      -0.285                -0.285




                                                       www.bornhorstward.com.au                                          Page 8

Used in these records

About this file

File size
18.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix D- Stormwater Management Plan.PDF · 18.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.