Noosa on Weyba
Stormwater Management Plan
                                                                                  ~,.., Cardno@
MUSIC modelling will be used to determine the reduction in       pollutant loads for the operational phase of
development.       This is the approach recommended     by  DEHP to determine whether     proposed treatment
devices will be sufficient. The resultant pollutant concentrations in the MUSIC modelling will be dependent
on the assumed default background concentrations within the treatment devices, which are in some

instances higher than the WQOs. For example the background TP concentration in bio-retention systems is
assumed to be 130 I-Ig/L. It is therefore not possible to show through MUSIC modelling that concentration
based WQOs can be met. Regular monitoring of water quality within Lake Weyba, conducted by Healthy

Waterways will be utilised to determine whether there is an impact from development, which will indicate that
the treatment measures being implemented on site should be reviewed.

Water quality monitoring of the existing waterbodies within the site will be conducted prior to development to
determine suitable discharge turbidity levels during the construction phase.   Monitoring of TSS, TP, TN and
gross pollutants is also recommended during this stage to define the existing water quality.

Event based (i.e. greater than 30mm rainfall in 24 hours) water quality monitoring of the waterbodies within
the site should be conducted for TSS, TP, TN and gross pollutants to ensure that the above water quality
concentration objectives are met.




Northbrook Corporation Pty Ltd                     Version 2                                   29 November 2012

SMP_v2.docx                                 Commercial in Confidence                                    Page 8

Used in these records

About this file

File size
52.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 9 of 37 Appendix 7 - Stormwater Management MCU12_0208.pdf · 52.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.