Noosa on Weyba
Stormwater Management Plan
                                                                                             ~,.., Cardno@


6              Proposed WSUD Strategy

6.1            Summary
The proposed WSUD features are shown in Figures 3, 4 and 5. In summary the WSUD strategy for the site
included:

>   Community Education.          The most effective treatment measure is to reduce the source of pollutants.
    Therefore community education is proposed          so that   residents are informed about what they can do to
    reduce their impact on their surrounding environment.           Information signs will be located at stormwater
    devices. An information leaflet will be distributed to each residence prior to the wet season each year.
    An example of the information leaflet is contained in Appendix C. As the development is a Community
    Title Scheme the body corporate will also be able to instigate appropriate measures to reduce pollutant
    loads from communal areas.

>   Reducing Potable Water Demand. Water efficient devices and appliances will be installed in each
    residence. Drought tolerant gardens will also be recommended.

>   Providing an Alternative        Water Source.       All   practically   available roof   area   will be connected to
    rainwater tanks that will be larger than QDC requirements, so as to maximise rainwater harvesting on
    site, minimise potable water demand and reduce the volume of stormwater discharged from site.
    Rainwater tanks will be used for toilet flushing, laundry and irrigation purposes.

>   Bio-retention Basins. Bio-retention basins are located at the end of the stormwater line, upstream of the

    point of discharge from the site. Stormwater ponds in the basins before slowly percolating through the
    vegetated filtration media and being treated through bio-filtration processes. Filtered stormwater is
    collected by perforated pipes and the discharged from site. Coarse sediment forebays will be located at
    the inlet points to capture sediment and prevent blockage of the filter media.

>   Bio-retention Gardens. Bio-retention gardens are small bio-retention basins that double as landscaped
    areas within     the road reserve.   They will treat runoff through bio-filtration before it is discharged to the
    stormwater system. Bio-retention gardens are suitable is relatively flat areas.

>   Bio-retention Tree Pits.  Bio-retention tree pits are trees located within filter media within the road
    reserve. They can provide some pre-treatment of runoff from the road prior to it being discharged to the
    stormwater system. Additional treatment will be required downstream. Tree-pits can be located in

    moderately sloped areas.
>   Bio-retention Swales.        Bio-retention swales are like standard vegetated swales but with a filter media

    layer to provide additional treatment of stormwater.        They are typically located along road-sides and can
    be used in flat to moderately sloped areas (around 2 percent).

>   Vegetated Swales. Vegetated swales will be used where underdrainage or slope requirements make the
    use of bio-retention swales
                            impractical.
>   Litter Baskets. Bio-retention basins and gardens are generally sufficient to capture any gross pollutants
    or litter from   urban areas. However, as an additional treatment measure litter baskets will be installed on
    the field inlets of bio-retention    gardens, swales and basins, as well as any other stormwater outlet
    discharging to the receiving waterways.
>   Revegetation of Lake Weyba Buffer Area.              A 40 metre wide lake buffer will be located along Lake

    Weyba.     This will   provide additional treatment of stormwater that may overflow from the adjacent bio-
    retention swales located in the 10 metre stormwater treatment zone. The buffer area, which has mostly
    been cleared of  vegetation for use as cattle grazing, will be revegetated, which                    will   improve its
    performance as a buffer treatment area, and improve bank stabilisation.




Northbrook Corporation Pty Ltd                          Version 2                                         29 November 2012

SMP_v2.docx                                      Commercial in Confidence                                            Page 9

Used in these records

About this file

File size
52.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 9 of 37 Appendix 7 - Stormwater Management MCU12_0208.pdf · 52.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.