Minor Change Existing Approval 51983 3225 21 [As Published] · 51983.3225.21

of 18

Text shows just the words. Original shows the document exactly as it was published.

                      Privacy – Unit 17
               12     To ensure privacy is protected between adjoining units, the kitchen window located on Level
                      1 must either:
                      a.      have a minimum window sill height or 1.7 metres above floor level; or
                      b.      be fitted with opaque glazing.
               13     The balcony located on Level 1 and the roof top terrace must include either balustrading or
                      fixed external screens, positioned in such a way to obscure direct views into the habitable
                      room windows or private open space areas of the adjoining units.
                      Noise
               14     Written certification is required from a suitably qualified person confirming that sound
                      pressure levels from all mechanical plant and equipment comply with the following:
                      a.      Air-conditioning
                              •        7am to 10pm: Maximum level allowable = background + 5dB(A)
                              •        10pm to 7am: Maximum level allowable = background + 3dB(A)
                      b.      Pumps/spa equipment
                              •        7am to 7pm: Maximum level allowable = background + 5dB(A)
                              •        7pm to 10pm: Maximum level allowable = background + 3dB(A)
                              •        10pm to 7am: No audible noise.
               15     The certification must be submitted to Council at the completion of the building works, which
                      certifies that operational noise from any fixed plant and equipment complies with the
                      requirements of this Decision Notice.
                      Landscaping Works
               16     The Cocos palm on Lot 17 must be removed prior to construction works commencing on site.
               17     The Hills Fig tree on Lot 17 may be removed as part of preparing the site for construction.
               18.    The development site must be landscaped generally in accordance with Planning Scheme
                      Policy PSP03 – Landscaping Plants and guidelines and the following requirements:
                      a.      Lot 17 - 2 x 45L Small Leaf Lilly Pilly’s (Syzygium luehmannii) planted in the general
                              location of the vegetation approved for removal.
                      b.      Lot 17-3 x 45L trees listed in the PSP03 suitable for the Noosa Heads locality must be
                              planted between the building and the northern boundary and north western corner of
                              Lot 17 that grow to a maximum height of 7 metres.
                      c.      Lot 19 - the works as generally shown on the approved Landscape concept plan as
                              prepared by Louise Custance except for the usage of exotic species and include 2
                              advanced local native tree species in a pot size of no less than 45L that grow to a
                              maximum height of 7 metres.
                      d.      Lot 19 – Landscaping must be provided between the building and western boundary
                              that grow (on average) to a maximum height of 5 metres in order to soften the built
                              form where viewed from the west.
               19.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               20.    Landscape works must be completed prior to the commencement of the approval use.
               21.    Vegetation to be retained must be protected from clearing or construction activities by:
                      a.      clearly marking vegetation to be retained with flagging tape


                                                                                                      Page 10 of 18
Document Set ID: 23671723
Version: 4, Version Date: 03/04/2025

Used in these records

About this file

File size
202 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51983 3225 21 [As Published].pdf · 202 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.