Submit a Construction Management Plan to Council prior te the pre-start meeting. The
Consiruction Management Plan must specifically address the following:

a. traffic management during all aspects of the construct phase including:

i. a Traffic Management Plan in accordance with Manual of
Uniform Traffic Control Devices (MUTCD) detailing ail
temporary signage and traffic control measures prior io
construction;

ii, maintenance of safe vehicle and pedestrian access across
the frontage of the site both during claily construction and
after daily construction has ceased;

iil, proposed fencing to the site during the construction phase of
the development;

iv. adequate parking arrangements for construction workers
and deliveries; and

¥. no queuing of trucks is permittec! on residential streets;

b. maintenance and protection of water quality and existing drainage lines
through the construction site through the implementation of appropriate
erosion and sediment contro! measures;

c. works programme identifying key components of the works and their
respective durations;

d. establishment of a communication protocol with the general public,
adjoining awners, emergency services and local businesses to acivise of
agreec' construction times, impacts on traffic and services and other
relevant issues;

e. include a post out to the local residents and businesses advising of the
proposed development, the expected time frames and the site contact
details,

f. include signage in prominent iocations on the boundaries of the site
advising of the proposed development, the expected time frames and the
site contact details;

g. identification of complaint management procedures including:

i. confact details for the on-site manager; and
ji. dispute resolution procedures.

h. details on the location of external fill/dump sites/sources, the haulage
route, type of vehicle to be utilised during filling operations and frequency
of usage.

Surveyor Pty Ltd | ABN 97625813998
30 Pottery $i Pomona Q 4568

M 0477 925 871 | E: briannaismith11@qmail. se"

 
 
  

 

Log in to download the original (3365 change representations seeking negotiated decision notice Op Works issue_signed.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.