Delegated Report - Code - Planning OPW26 0055 (As Published)

of 8

Page text shows just the words. Original shows the document exactly as it was published.

               response was not satisfactory in addressing these two sections of QUDM and therefore a condition
               is recommended requiring the certifying RPEQ to certify the system complies with these sections.
               Engineering is generally satisfied that the proposal complies with the relevant provisions of The
               Noosa Plan 2020 and recommends the following conditions.
               5.      CONSULTATION
               5.1. Referral Agencies
               Not Applicable
               5.2. Internal Council Referrals
               Not applicable
               6.      CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW26/0055 for Operational Works - Stormwater situated at 85
               Gympie St Tewantin Qld 4565 and described as Lot 51 SP 260161, it is recommended the
               application be approved in accordance with the following details for the Decision Notice:
               1.      APPLICATION DETAILS

                   Application No:                  OPW26/0055

                   Street address:                  85 Gympie St Tewantin Qld 4565

                   Real property description:       Lot 51 SP 260161

                   Planning Scheme:                 Noosa Plan 2020 (20 March 2026)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Approval for Operational Works - Stormwater
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                          Plan No.              Rev.     Plan/Document Name                      Date

                          22-0416-F22           F        Operational Works Stormwater Plan       2 June 2026
                                                         Prepared by Lindsay Consulting

                          22-0416-F25           F        Operational Works Stormwater Details    2 June 2026


                                                                                                      Page 4 of 8

Document Set ID: 24933421
Version: 2, Version Date: 09/07/2026
Log in to download the original file

Delegated Report - Code - Planning OPW26 0055 (As Published).pdf · 2.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.