Delegated Report - Code - Planning OPW26 0055 (As Published)
Prepared by Lindsay Consulting
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 8 July 2028, unless an application to extend the currency period is
approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
3. All necessary approvals from external service providers (e.g. Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
4. A condition report including photographs of the frontage of the site must be completed and
submitted to Council prior to any works commencing.
5. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to any works commencing in Council’s Road
Reserve.
6. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
7. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
8. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
9. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
10. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Works within Road Reserve/Reinstatement
11. Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out construction
works, Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
12. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
Page 5 of 8
Document Set ID: 24933421
Version: 2, Version Date: 09/07/2026