MCU14/0056 Response to SARA - Consulting Report

of 321

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (24.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 20, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                                                              ENG
                                                  Engineering Report & Stormwater Management Plan
                                          Date:          27/01/2015     Document No.:     14012-ENG-04.Docx

                                           By:              AvT          Revision No.:              F


     •    Drainage separation options may include grading, bunding, kerbing and/or
          channelling.
     •    Bulk fuel transfers shall be carried out in a defined Tanker Delivery Standing Area. This
          area shall normally be drained to the uncovered area stormwater treatment system.
          However, during fuel delivery operations, automatic diversion valves shall be used to
          divert such drainage to the under-canopy containment vessel. The Tanker Delivery
          Standing Area in uncovered locations shall be sized so that the drainage area has a
          radius of at least 3 meters and a storage volume equivalent to that of the largest
          tanker storage compartment that is expected on site at any given time
     •    Signs indicating fate of flow such as “flows to creek” shall be provided in locations
          around the uncovered area.

     Service Station Treatment
The fuel dispensing areas shall be graded to a suitable underground containment and
treatment vessel (i.e. sump/tank) compatible with petroleum products and other likely
chemicals. It is proposed that a SPEL Puraceptor containment system be installed to capture
and retain flows from the fuel dispensing areas.

The SPEL Puraceptor (model P.040.C1.2C) is a 6 minute full retention tank that will hold and
treat all the stormwater runoff from the associated forecourt area catchment area of 538m2.
Based on a rainfall duration of 5 minutes and a rainfall intensity of 245 mm/hr for 20 ARI the
associated runoff is approximately 37l/s. The proposed SPEL Puraceptor P.040.C1.2C can treat
up to 40l/s, therefore it is considered to be suitable for this application.

The SPEL Puraceptor P.040.C1.2C has a spill containment capacity of 9000l which is sufficient
to hold the contents of a fuel tanker in case of an emergency spill.

Refer to Appendix F for the “SPEL Risk Assessment Report for Proposed Service Station
Located at Corner Myall Street & Ferrells Road, Cooroy, QLD” which provides details on the
proposed system and also the stormwater quality treatment provided by the system.

Refer to Appendix F for the “SPEL Puraceptor Operations and Maintenance Manual”.

     Alternative Service Station Treatment
Should the SPEL Puraceptor with the accompanying report in Appendix F not be acceptable to
council, then the runoff from the refuelling areas will be directed to a blind sump holding tank
that is not connected to the stormwater system or the sewer system.

       Car Wash Treatment
It is anticipated that the water supply for the proposed car wash will be obtained from a
combination of council water, captured roofwater and water reuse. The car wash treatment
and water reuse for this proposed development will be by others during the detailed design
phase of the project and will be subject to plumbing approval.




A PO Box 26, Carina Q 4152                                                                   19 | P a g e
E [email protected]
W www.vtce.com.au
Log in to download the original file

MCU14_0056 Response to SARA - Consulting Report.pdf · 24.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.