Corner Myall Street & Ferrells Road Cooroy, QLD 4563
SEQwater Development Guidelines
Development Guidelines for Water Quality Management in Drinking Water Catchments
Table 8 Element 5: Water Sensitive Design and Stormwater/Runoff Management Specific Outcomes and
Measures cont.
Specific Outcome Measures Comment
M24.8 Stormwater management measures for
construction are used in locations where they
remain in place for the duration of development
works and/or where permanent stormwater
controls will eventually be incorporated.
M24.9 Where permanent stormwater quality
management measures are required (structural and
non-structural), such are selected, constructed and
maintained in accordance with local government
requirements, manuals, guidelines and the like with
location and installation undertaken to prevent
erosion or contamination of runoff and as
appropriate to the existing and proposed features
of the site.
M24.10 Selection, design and installation of
stormwater management measures should reflect
the following principles:
a) Minimise areas subject to disturbance;
b) Maintain maximum protective vegetation using
selective clearing where appropriate, with
retention of native vegetation to maximise
infiltration;
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.