Engineering Report & Stormwater Management Plan
Date: 27/01/2015 Document No.: 14012-ENG-04.Docx
By: AvT Revision No.: F
A geotechnical investigation will be undertaken and a report will be prepared for the site prior
to starting the detailed design stage of the development to ensure that the earthworks and
erosion control measures are designed to suit the site conditions.
4. Roadworks
The proposed development fronts onto both Myall Street and Ferrells Road. External
roadworks are proposed for this development in accordance with the traffic impact
assessment report by Pekol Traffic and Transport, project number 13-081.
A new left turn auxiliary deceleration lane (AUL) into the new development is proposed for
traffic travelling from South to North along Myall Street. Dimensions are outlined in the traffic
impact assessment report and to be detailed as per Austroad’s: Guide to Road Design
Manuals. A channelised right turn treatment (CHR) is proposed for Myall Street at the
entrance to the new development. This is for traffic travelling from North to South along
Myall Street. Dimensions are outlined in the traffic impact assessment report and to be
detailed as per Austroad’s: Guide to Road Design Manuals.
No external roadworks are proposed for Ferrells Road.
Internal roadworks are required for the new proposed multi-use development. Refer
attached Appendix B for proposed layout plans and details. Line marking and signage will be
used through the new proposed development to emphasise the intended direction of
vehicular flow in accordance with the Manual for Uniform Traffic Control Devices (MUTCD).
A PO Box 26, Carina Q 4152 7|P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.