OPERATIONAL PLAN 2018-19 PROGRESS REPORT
LONG TERM PLANNING FOR NOOSA SHIRE
No. Project Responsibility Update A) Fit]
1 Complete State interest review and community Director Environment & Sustainable State Interest review underway. State agencies provided initially close to 150 Ontrack @
consultation for draft new Noosa Planning Scheme Development comments. All of these matters have been resolved or responded to and a
revised scheme was sent back to the State in September 2018 informed by a
number of workshops with Councillors. Awaiting Minister's approval to
consult with community.
2 Progress remaining matters associated with the Property Manager The primary action plan for the Foreshore Plan comprised the 10 items in On track Qo
Noosaville Foreshore Land Use Master Plan Council's resolution. All have been actioned, and those requiring
ownership/action by other departments (Items E, F, G & H) have been
discussed with those departments to progress.
3 Implementation of Noosa Transport Strategy priority Director Infrastructure Services Five initiatives as work in progress. 2018/19 Christmas period short term On track oO
actions traffic planning proposals are underway.
4 Commence the Noosa North Shore Campground Property Manager Land tenure issues have delayed process. Tender documents are currently Behind Schedule Oo
redevelopment being finalised with tender expected to be advertised at the end of October
2018.
5 Complete detailed Asset Management Plans Asset Planning Manager Council recently adopted the Road Bridges Asset Management Plan at the Behind Schedule Oo
August 2018 Council meeting. Ongoing development of the Roads,
Stormwater and Buildings & Facilities Asset Management Plans are to be
rolled out throughout the remainder of the year. However data reconciliation
has increased the time frame for the delivery of the remaining Asset
Management Plans.
6 Finalise Climate Change Adaptation Plan and initiate Director Environment & Sustainable A review of one set of hazard modelling results revealed re-modelling with Behind Schedule Oo
implementation of actions Development revised parameters is required. Negotiations with State regarding calibration
of new parameters, plus the re-modelling, has delayed the CHAP by 5 weeks.
Work on risk assessments for the CCAP progressing as per schedule.
Page 90 of 97See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.