GOOD SHEPHERD LUTHERAN COLLEGE ODYSSEY CONSULTING GROUP
Lot 30 on SP170751 Conceptual Stormwater Management Plan
115 Eumundi Noosa Road, Noosaville Project No: K4277
Coefficient of Runoff
The post development coefficient of runoff (C year) was determined based on the fraction impervious
(fi) method as specified in QUDM. Using a one hour, ten year rainfall intensity (1I10) of 72.3 mm/hr, the
following coefficient of impervious (C10) values have been adopted for the post development
scenario.
Table 5: Post Development Catchment Impervious Properties
Catchment Impervious Area (m2) Catchment Area (m2) Fraction Impervious C10
A 3092 3,878 0.80 0.86
B 592 889 0.67 0.83
C 0 247 0.00 0.70
With reference to QUDM Table 4.5.2, by applying the frequency factors for the standard storms of 2,
5, 10, 20, 50 and 100 years result in the following post development coefficients of runoff as shown in
Table 6.
Table 6: Post Development Coefficients of Runoff
Catchment 2 5 10 20 100
A 0.73 0.82 0.86 0.90 1.00
B 0.71 0.79 0.83 0.87 1.00
C 0.60 0.67 0.70 0.74 0.84
Time of Concentration
Post development catchments A & B consist of paved areas and have therefore been assumed to have
a standard time of concentration of five (5) minutes as per T.4.6.2 – Recommended standard inlet
time. The time of concentration for Catchment C is indicated below in Table 7.
Table 7: Catchment C Time of Concentration
Time of concentration
Catchment Catchment
Catchment Overland flow Concentrated flow
Area (m2) Properties Total tc
Friend’s Equation QUDM Figure 4.09
Horton’s (n) = 0.035
Light cover
L=5m
C 247 bushland / poor n/a 5 min
Slope = 6%
grass cover
t = 4.5min
Design Flow Rates
Design storm flow rates have been calculated for standard storms with an ARI of 2, 5, 10, 20, 50 and
100 years for the post development case using design rainfall intensities from the Bureau of
Meteorology. The Rational Method (Q = 2.78 x 10-3 CIA) has been used to calculate the required
design flow rates for the subject site. The calculated post development peak flows for Catchment A, B
and C are presented in Table 8, 9 and 10 respectively.
Table 8: Catchment A Post Development Peak Flow Rates
Average Recurrence Interval ARI 2 5 10 20 100
Coefficient of Runoff C 0.73 0.82 0.86 0.90 1.00
Average Rainfall Intensity
I 164 202 223 253 321
(mm/h)
Area of Catchment (ha) A 0.388 0.388 0.388 0.388 0.388
Peak Flow Rate (m3/s) Q 0.129 0.178 0.207 0.246 0.346
K4277-0002-E 18 June 2019 Page 5 of 14
Document Set ID: 20894174
Version: 1, Version Date: 03/07/2019
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Plans - MCU18-0097.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.