Water Quality Devices
73. Water quality control devices shall be installed generally in accordance with the Stormwater and Water
Quality Management Plan. Detailed staging plans and specifications, based on and generally in
accordance with the Plan shall be prepared and submitted (after consultation with officers of the Council)
with the relevant applications for operational works.
Drainage Works
74. The Developer shall complete the drainage works progressively in conjunction with development of the
site and generally in accordance with the approved Stormwater and Water Quality Management Plan.
Detailed drainage plans and specifications, based on and generally in accordance with the approved
Drainage Plan, the EMP and these Conditions, shall be prepared and submitted (after consultation with
officers of the Council) with the relevant applications for operational works.
75. All drainage works as required by the Drainage Plan shall be provided by the Developer at its own cost.
76. A holding tank shall be provided on site with a capacity to hold at least 20,000 l for the purposes of
providing a water supply for non-potable uses such as landscaping.
Land Development
Vehicle Access
77. A 5.5 metre wide concrete crossover driveway shall be constructed from Serenity Close generally in
accordance with Council’s Standard Drawing 9002.
78. The driveway shall be designed and constructed to Council’s design standards and to grades that prevent
vehicles from scraping and/or bottoming whilst also allowing pedestrians movements along the footpath
without any level difference. Should any driveways be constructed to grades that do not comply with
Council’s Standards or AS2890.1-2004, Council will require that the driveway be removed and
reconstructed to levels that do comply.
Please note, a step between the driveway and the footpath shall be avoided, as it is preferred to have the
footpath continue at a constant grade to minimise the potential for pedestrians to trip or fall.
79. All vehicles shall enter and leave the site in a forward direction.
80. Full engineering details of the proposed driveway and carparking area shall be submitted for approval
prior to obtaining a Development Permit for Operational Works.
Internal Driveways
81. The development shall have an internal driveway that complies with the requirements of AS2890.1-2004.
Mark lining between the ingress and egress lanes through the bend in the driveway within the basement
carpark shall be required to sure safe passage of vehicles on both lanes.
Service Bay
82. One of the 5-carparking spaces, towards the frontage of the development, shall be used as a shared
service bay for small delivery/maintenance vehicles. This space shall be clearly line-marked and sign
posted for use by Service Vehicles between the hours of 6am to 6pm. Outside of the specified hours the
space could be used as a standard visitor space.
Carparking
83. Carparking shall be provided within the site as generally shown on drawings number 02.01 Issue A1 and
02.02 Issue A dated May 2007 prepared by Settler’s Cove, except as modified herein.
84. A minimum of 56 carpark spaces shall be provided on site, comprising:
84.1. 51 covered carpark spaces (within the basement), consisting of 26 resident spaces and 25 visitor
spaces (including 1 disabled space).
84.2. 5 uncovered carpark spaces for short term parking (towards the frontage of the development),
consisting of 4 standard spaces with 1 disabled space.
SEP o:\database\onestop\decision.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
23117 DA COMPILED Decision Notice [As Published]Related documentApplication case desk ↗
0015CF9F.001.pdfRelated documentPublic source context ↗
About this file
- File size
- 87 KB (small file)
- File type
No other editions are linked here.