SECTION 9- CONSTRUCTION 9.3 FLOORS
9.3.1 General
OF ANNA PAROZ DESIGN AND DRAFTING ©
9.4 WALLS
REQUIREMENTS FORBAL—FZ This Standard does not provide construction requirements for concrete slabs on the ground. 9.4.1 General
9.3 FLOORS The exposed components of external walls shall be as follows:
SELECTED CONSTRUCTION MATERIAL SUMMARY (a) Non-combustible material including the following provided the minimum thickness is 90 mm:
Lower Level is slab on Ground
AS 3959:2018. (i) Full masonry or masonry veneer walls with an outer leaf of clay, concrete,
A building assessed in Section 2 as being BAL—FZ shall conform with Section 3 and calcium silicate or natural stone.
Clauses 9.2 to 9.8 and have a minimum setback distance of 10 m from the edge of the (ii) Precast or in situ walls of concrete or aerated concrete.
classified vegetation. (iii) Earth wall including mud brick.
In circumstances where the 10 m setback distance between the building and the edge of the or
classified vegetation cannot be achieved, those elements of the building that are less than (b) A system conforming with AS 1530.8.2 when tested from the outside.
10 m from the edge of the classified vegetation shall conform with AS 1530.8.2. or
The details for roof systems specified in Appendix H are the result of testing to (c) A system with an FRL of 30/30/30 or –/30/30 when tested from the outside.
AS 1530.8.2 and are deemed to satisfy solutions for the purpose of this Standard. or
Decking -
(d) A combination of any of Items (a), (b) or (c).
Any element of construction or system that satisfies the test criteria of AS 1530.8.2 may be James Hardie - Hardideck
used in lieu of the applicable requirements contained in Clauses 9.2 to 9.8. 9.3.2.2 Unenclosed subfloor space 9.4.2 Joints
NOTES: Where the subfloor space is unenclosed, the floor system, including bearers, joist and All joints in the external surface material of walls shall be covered, sealed, overlapped,
G:\_UserData (CURRENT)\Documents\1. Desktop from Old Computer (CURRENT)\Desktop (Current)\ANNA'S Comp SD (Current)\2025 Current Design Jobs\Mitton Cameron, Karen Tinbeerwah 2025\Mitton 2 Shed House.rte
1 BAL—FZ is primarily concerned with protection from flame contact together with ember flooring, shall— backed or butt-jointed to prevent gaps greater than 3 mm
attack and radiant heat of more than 40 kW/m2. (a) have an FRL of at least 30/30/30 and the surface material shall be non-combustible;
2 Construction in BAL—FZ may require reliance on measures other than construction. The or
requirements for construction of a building BAL—FZ may be regulated by the building (b) have the underside of the combustible elements of the floor system protected with a (Ref to 9.4.2.2) WALL A - STONE
authorities having jurisdiction in the States and Territories of Australia. 30 min resistance to incipient spread of fire system; or Compliant with (i) Full masonry or masonry veneer walls with an outer leaf of
JAMES HARDIE LINK FOR MORE FZ OPTIONS : (c) conform with AS 1530.8.2 when tested from the underside; or clay, concrete, calcium silicate or natural stone.
https://www.jameshardie.com.au/ContentfulCMS/Technical- (d) be a combination of any of Items (a), (b) or (c).
Library/Bushfire_Prone_Area_Technical_supplement.pdf (Ref to 9.3.2.2) UNDERSIDE Treated as Eaves by JAMES HARDIE
(Ref to 9.4.2.2) WALL B - Colorbond Cladding Compliant with...
9.2 SUB-FLOOR SUPPORTS
This Standard does not provide construction requirements for subfloor supports where the
subfloor space is enclosed with a wall that conforms with Clause 9.4.
Where the subfloor space is unenclosed, systems, including support posts, columns, stumps,
piers and poles, shall—
(a) have an FRL of at least 30/–/– and shall be non-combustible; or
(b) be a system conforming with AS 1530.8.2; or
(c) be a combination of Items (a) and (b).
NOTE: This requirement applies to the subject building only and not to verandas, decks, steps,
ramps and landings (see Clause 9.7).
C9.2 Combustible materials stored in the subfloor space may be ignited by embers and
impact the building.
ALFRESCO & DECK POSTS as NASH STANDARD
STEEL POSTS
AS 1530.8.2:2018
The methods for fire tests on building materials, components and structures, Part 8.2: Tests on
elements of construction for buildings exposed to simulated bushfire attack — Large flaming sources
This Standard provides methods for determining the performance of external construction
elements when exposed to direct flame impingement from the fire front.
CLIENT: JOB DRAWN BY: DATE DRAWN: CHECKED BY: APPROVED FOR
NOTES: DESCRIPTION : CONSTRUCTION:
PLEASE NOTE: DETAILS SHOWN ON THESE PLANS ARE CAMERON & KAREN MITTON AP 08.04.25
INTENDED
CUSTOM DESIGN - BAL FZ
TO BE ACCURATE - HOWEVER INFORMATION WRITTEN INTO 56 OYSTER BANK ROAD, SITE ADDRESS: NOT FOR CONSTRUCTION COUNCIL AREA: SCALE:
INDIVIDUAL CONTRACTS WILL TAKE PRECEDENCE OVER PLANS BLI BLI, QLD 4560 RP186535 NOOSA SHIRE
PROGRESSION STAGE : WORKING DRAWINGS 1
* ALL DIMENSIONS ARE IN MILLIMETRES TELEPHONE : 0412 105 174
* DO NOT SCALE - USE WRITTEN DIMENSIONS 7 ASHDOWN COURT, TINBEERWAH DRAWING TITLE: JOB No: DRWG No: ISSUE:
EMAIL : [email protected]
* ALL DIMENSIONS ARE TO STRUCTURAL FRAMES ONLY QLD, 4563 A0068724 2.3 Lr
EXCLUDING FINISHED (EXISTING) SURFACES Building Design Licence no. 1269235 (Low Rise) BAL FZ CONSTRUCTION. Pg. 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.