b. comprise feature vegetation (either existing or planted) in preference to built forms
c. integrate with the landscape design of the balance of the estate
d. be constructed of durable and low maintenance materials
e. be treated with a graffiti resistant coating
f. not restrict pedestrian access
g. Any estate entrance works must be undertaken in accordance with an Operational
Works approval.
Easements
39. A 20 metre wide continuous easement for fire break trail purposes must be registered against
the title of each new lot. The easement must be:
a. In favour of Council and Fire Services
b. Located over the land area defined by ‘Firebreak fire trail’ on the subject site identified
on the Fire Break Trail Specification within the approval plans
c. Located outside of the proposed covenant area;
d. Have no fencing between lots;
e. A continuous alignment through the lots.
40. The Grantor is responsible for all maintenance and costs associated with the 20 metre wide
easement.
41. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
Bushfire Management – Reconfiguration Requirements
42. All reconfiguration works must be carried out in accordance with the approved Bushfire
Hazard Assessment and Management Plan.
*(Refer Advisory Note)
43. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the bushfire management conditions
of this Decision Notice.
*(Refer Advisory Note)
44. The following clauses must be included in the contract of sale for all Lots which requires:
a. future dwellings to be constructed within the building envelopes shown on the
Approved Plans AND in accordance with the approved Bushfire Hazard Assessment
and Management Plan.
b. the trafficable fire break trail to be maintained, include unlocked 4m wide gates allowing
access to Council and Fire Services and ensure compliance with the QLD SPP
Bushfire 2019 firebreak trail specifications.
c. All future dwellings are to provide a dedicated 10,000 litre water supply for firefighting
purposes .
45. A Landholder Bushfire Information Kit is to be provided to all new owners detailing the
performance requirements of the trafficable firebreak fire trails
Page 17 of 68
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.