Council archive · source document
Recommendation - Noosa Iconic Panel - 010.2009.00000982.001 [As Published] · 142009.982
Officer: Denis Wallace
Direct Telephone: (07) 5449 5179
Response Address: Locked Bag 72
Sunshine Coast Mail Centre QLD 4560
Email: [email protected]
Our Reference: 2009/982
Your Reference:
8 January 2010
Kristian Baker
Project Manager
Noosa Iconic Panel
PO Box 15009
CITY EAST QLD 4002
Dear Sir
Recommendation - Noosa Iconic Panel
Iconic Queensland Places Act 2008
I refer to Application No. 2009/982 as detailed below and wish to advise that Council completed an
assessment of the development application on 6 January 2010.
Council’s recommendation is set out below.
0 APPLICATION DETAILS
Application No: 2009/982
Street address: 222 Gympie Terrace, Noosaville
Real property description: Lot 160 CP 908649
Planning Scheme: The Noosa Plan
0 COUNCIL’S DECISION DETAILS
The following type of approval is recommended:
Development Permit for Operational Works - Prescribed Tidal Works - Extensions to
Commercial Jetty
0 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the recommended conditions.
0 COUNCIL’S RECOMMENDED CONDITIONS
0. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table and as
may be amended by these conditions.
Plan No. Rev. Plan / Document Name Date
09/161-1 - “O” Boats Proposed Extensions John Norden & October 2009
No.222 Gympie Terrace Associates
Noosaville
Page 1 of 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 12 pages
Page 2
09/161-2 - “O” Boats Proposed Extensions John Norden & October 2009
No.222 Gympie Terrace Associates
Noosaville
2. All structures associated with the use (jetty and pontoons) must be constructed wholly within
the lease area as shown on CP908649.
3. The jetty and pontoons shall be licensed with the Council upon completion of the structural
work and shall be licensed annually thereafter.
4. To ensure the safety of persons accessing the approved works and to prevent environmental
harm, a safety audit of the on-site fuel storage tanks, bowsers and associate pipework, valves,
vents and systems shall be conducted by a suitably qualified professional and submitted to
Council for approval. The audit shall demonstrate that the fuel systems are in a safe and
serviceable condition or, where necessary, identify repair and rectification requirements to
meet the relevant Australian Standards and industry best practice environmental
management. Any repair works must be completed, with certification submitted by the auditor
to Council, prior to the use of the new works (pontoon/jetty extensions).
5. Structures shall designed and constructed such that they are free standing within the
waterway and are not connected to or behind the revetment wall or rock wall.
6. No posts or vertical supports of the proposed structures are to extend vertically above the height
of the existing piles.
7. No boatlifting devices are to be attached or moored at the jetty structure for the purpose of
elevating a vessel above the water without Council approval.
8. The jetty shall be constructed in a manner to render the underside area vermin proof.
9. The connection point for any electrical reticulation system extending beyond the revetment
wall must be located above the Q100 flood level.
10. Lighting associated with the use shall be designed, installed, operated, and maintained in
accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting.
11. Boat repair activities will not be permitted on site.
12. Wastewater and sullage shall only be disposed of at approved pumpout facilities.
13. The mooring facility shall not be utilised for live-aboard purposes.
14. Any construction and post construction activity is not to impact on the condition of the
waterway, and is to be conducted so as not to breach the Environmental Protection Act (EPA)
1994 and the Environmental Protection (Water) Policy 1997.
15. The approval or conditions do not constitute a ruling on structural safety and the applicant
must make their own arrangements to ensure adequacy of design and work. The granting of
the approval does not warrant that the plans and specifications have been checked in detail,
nor does it absolve the owner of the land from complying with all the conditions of this
approval and/or relevant Council By-Laws and Policies and/or relevant statutes and/or
statutory regulations in the execution and/or performance of the works. The Council does not
accept any responsibility for the accuracy of such plans and specifications as approved.
16. Certification by a Registered Professional Engineer of Queensland shall be submitted to
Council prior to the return of any bond monies held by Council. The certification shall state that
the works have been constructed in accordance with best practice methods, are in accordance
with Coastal Protection and Management Act 1995, are structurally sound and will have no
detrimental affect on the river bed or river bank.
Page 2 of 13
Page 3
17. A final inspection and approval of the structure by Council’s Inspector is required prior to the
return of any bond monies held by Council. Please contact Council’s Planning Assessment
Section to arrange the inspection.
18. The Development Permit for Operational Works lapses if the works have not been completed
by 5 February 2012, unless an application to extend the currency is approved by Council.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Tidal Work that is Concurrence Qld Transport (Maritime MacArthur Avenue East
prescribed tidal work Safety) PINKENBA QLD 4008
Tidal Work that is Concurrence Department of EcoAccess
prescribed tidal work Environment & Resource GPO Box 15155
Management CITY EAST QLD 4002
A copy of any referral agency conditions is attached.
6 APPROVED PLANS/DOCUMENTS
The plans and / or documents recommended for approval are listed in the following table:
Plan / Document No. Rev. Plan / Document Name Date
October 2009
09/161-1 - “O” Boats Proposed Extensions No.222
Gympie Terrace Noosaville - John
Norden & Associates
October 2009
09/161-2 - “O” Boats Proposed Extensions No.222
Gympie Terrace Noosaville - John
Norden & Associates
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a Change to an Existing Approval Application under the Integrated
Planning Act must be made. Amended plans clearly indicating the changes must be lodged with
this application along with the appropriate fees.
2. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
1.0. On a Sunday or public holiday, at any time; or
2.0. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
Page 3 of 13
Page 4
3. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if the
cost of operational works exceeds $80,000, then a portable long service leave levy is required to
be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the approved
form issued by the Building and Construction Industry (Portable Long Service Leave) Authority
that confirms that the requirements of the Act have been satisfied. A statutory declaration
outlining the cost of the operational works must be submitted to Council prior to commencement
of work.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
0 PROPERTY NOTES
Not applicable
0 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
0 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Not applicable
0 SELF ASSESSABLE CODES
The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Not applicable
0 SUBMISSIONS
Not applicable
0 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable
0 OTHER DETAILS
A copy of all supporting and common material for the application, including Council’s planning
assessment report is available on PD Online at:
http://rrif.noosa.qld.gov.au/masterviewpublic/modules/applicationmaster/default.aspx?page=wrapper
&key=014.2009.00000982.001
Page 4 of 13
Page 5
If you have any questions, please do not hesitate to contact me on 5449 5179.
Yours faithfully,
Denis Wallace
Senior Development Planner
Page 5 of 13
Page 6
Referral Agency Conditions
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
Page 6 of 13
[OCR of page images]
j Referral Agency Conditions
S U NS h | N € Coast INTEGRATED rane vy 1997 & 1998 REGULATION
Regional Council
Queensland
Government
30 November 2009 eee
River Ente Pry Lid Queensland Transport
222 Gympie Terrace
Noosaville Qld 4556
Dear Sir
Tidal Works — Request for comments — Extensions to Commercial Jetty, 222 Gympie Terrace
Noosaville. Application Number 2009/982.
Thank you for your emails of 18 and 19 November 2009 about your application to extend the jetty at
the location mentioned above.
As a concurrence agency under the Integrated Planning Act 1997 and Coastal Protection
Management Act 1995, Maritime Safety Queensland has no objection to the proposal provided the
following navigation and marine safety conditions are addressed.
1.
The construction must comply with Andrew McKellar Design, Drawing 02.00709.1.1A, attached
to your email dated 18 November 2009,
No part of the structure or any ship berthed at this structure is to extend beyond the boundaries of
the lease area as shown on the submitted water allocation plan 02 00709.1 1A
You, or your agent, must advise the Harbour Master, in writing, of the commencement date,
proposed timetable, and contractor contact details at least two weeks before commencing
construction.
You, or your agent, must issue any notices the Harbour Master requires
You, or your agent, must advise the Harbour Master, in writing, when you have completed
construction,
You or your agent must supply, install and maintain any navigation lights, buoys, marks or signs
the Harbour Master considers necessary. Any lights, buoys, marks and signs must accord with
Maritime Safety Queensland's requirements.
Mamime Safety Queensiand Ourref 7 10101645(3) P34868 EIS086 FIG
Marine Opsrabons (Brabene) Your ref
MacArtwr Avenue East Enquines Glenn Hale
Pinkenba Queensiand 4008 Telephone +61 7 3860 3665
Faceimie +61 7 3860 2671
‘ABN 43 200 330 620 Website waw meq qld gov au
Email glen n hale@maq qd gov au
Page 6 of 13
Page 7
Page 7 of 13 [OCR of page images] 7. You must adequately light the structure. The contractor must position all lighting so it does not cause a risk to the safe navigation of other vessels, Any freestanding piles must have retro- reflective tape fitted. 8. You, or your agent, must remove any obstructions and debris encountered during construction, and dispose of them, as the Harbour Master requires. 9, Any ships and equipment you or your agent use must comply with the Transport Operations (Marine Safety) Act 1994, the Transport Operations (Marme Safety) Regulation 2004 and the Transport Operations (Marine Pollution) Act 1995. 10. The contractor must complete construction within two years from the date of approval. If construction is not completed, you will need additional or amended comments from the Regional Harbour Master. Maritime Safety Queensland does not need to be further consulted if all of the above conditions are met. The above conditions must be included in your application to the assessment manager Yours sincerely Z2Zz. Gf « Captain Richard C Johnson Regional Harbour Master (Brisbane) Martime Satoty Quoensiand Page 2 0f2 Page 7 of 13
Page 8
Page 8 of 13 [OCR of page images] ecoaccess scx comesrnem vineniat hearers ard © $0032451 Concurrence Agency Response This notice 1s issued by the DERM pursuant fo sechons 3 3 16 and 3 3 18 of the Integrated Planning Act 1997 to advise of @ decision or achon The Chief Executive Officer cc Noosa River Enterprises Pty Ltd Sunshine Coast Regional Council 222 Gympye Terrace Locked Bag 72 NOOSAVILLE QLD 4566 Sunshine Coast Mail Centre QLD 4560 Attention Rod Baker Your reference 2009/982 Our reference IPCC01683209, MCY2217 Attention Denis Wallace Dear Sir or Madam Re: Referral for Concurrence Agency Response The Department of Environment and Resource Management (DERM) wishes to advise that the referral for a concurrence agency response, recerved on 16 November 2009, has been assessed, and the response to the application is detailed below 1. Property/Location: Street address - 222 Gympie Terrace, NOOSAVILLE LovPian - Lot 160 on CP908649 Waterway - Noosa River 2. Details of the recommendation Aspect of development - Concurrence response for operatonal work ~ Tidal work that 1s prescribed tidal work Recommendaton ~ Granted in full wath conditions DERM Reference Number - 1PCC01683209 3. Currency period This approval will lapse unless substantially started vathin the currency period/s set by the Assessment Manager or the standard currency penods stated in section 3 5 21 of the Integrated Planning Act 1997 applying to each aspect of development in thes response cao Queensland Government “Depertmert of Envronment 8 Resource Management Department of Environment & Resource Managemert wwe deem ald gov au ABN 46 640 294 485 Page 8 of 13
Page 9
Page 9 of 13 [OCR of page images] ecoaccess erence iS lrervos art partrals 4. The approved plan(s) The approved plan(s) and/or document(s) for thrs response Plan/Document No. | Plan/Document Name 02 00709 1 1A Site Plan July 09 5. Codes for self-assessable development Any self-assessable development for an environmentally relevant activity conducted in congunction with this response, must comply with the relevant code of environmental compliance 6. Assessment Manager Responsibilities Please note that it is a requirement under Sections 3 5 15 and 3 5 17 of the Integrated Planning Act 1997 that a copy of the final Decision Notice (which includes DERM’s concurrence response) for this application issued by the Sunshine Coast Regsonal Council, be forwarded to each referral agency In addition, the State's Native Title Work Procedures indicate that responsibility for assessment of native title issues for an IDAS application rest with the Assessment Manager Therefore wn this instance, DERM has not provided a notification to native title partes If you require more informabon, please contact Leome Crane, the Project Manager, on the telephone number ksted below Yours sincerely Ben Sale Delegate Department of Environment and Resource Management Date: Oye (Ht. Enquiries: DERM South East Region PO Box 168, Cotton Tree MAROOCHYDORE QLD 4658 Phone (07) 5459 6135 Fax (07) 5443 9927 Page 2 of 2 Department of Environment and Resource Management Page 9 of 13
Page 10
Page 10 of 13 [OCR of page images] Concurrence Agency Response Section 3.3.16 and 3.3.18 of the Integrated Planning Act 1997 DERM Permit number: 1PCC01683209 Assessment Manager 2009/9882 reference: Date application 16 November 2009 received by DERM: Permit Type Concurrence response for operational works Relevant Laws and Coastal Protection and Management Act 1995 and any subordinate Policies: legisiation Jurisdiction: Item 12 of Table 2 of Schedule 2 of the Integrated Planning Regulation 1998 This response attaches to the land described below Descri River Ltd 1 CP908649 River of to a commercial in Noosa River for the of vessels Reasons for inclusion of development conditions In accordance with section 3 3 18(7) of the integrated Planning Act 1997 and section 278 of the Acts Interpretation Act 1954, the reasons for the inclusion of development conditions are The Department of Environment and Resource Management (DERM) is a concurrence agency under the Integrated Planning Regulabon 1998 for coastal management under the Coastal Protection and Management Act 1995, excluding amenity or aesthetic significance or value Additional information for applicants Other approvals This concurrence response pursuant to Section 104 of the Coastal Protection and Management Act 1995 does not remove the need to obtain any further approval for this development which may be required pursuant to this or other legislation, both State and Commonwealth Applicants are advised to check with all relevant statutory authorities for such approvals as may be required Contammated Land ites a requirement of the Envwonmental Protection Act 1994 that if an owner or occupier of land becomes aware a Notifiable Activity (as defined by Schedule 3 of the Environmental Protection Act 1994) is being carned out on the land or that the land has been affected by a hazardous contaminant, they must, within 22 days after becoming so aware, grve notice to the DERM ee Queensland Government Department of Enwronment & Resource Management Department of Envrorenent & Resource Management swwew deem gid gow au ABN 46 640 24 435 Page 10 of 13
Page 11
Page 11 of 13 [OCR of page images] Concurrence agency response DERM Permit number: IPCC01683209 CONDITIONS OF APPROVAL General 1 All works are to be constructed in accordance with the approved drawings and the specifications as detailed on these drawings 2. If acid sulphate sols are found to be present through testing of areas subyect to excavation in accordance with the requirements of State Planning Policy 2/02, then the works must be managed to prevent acd sulphate soi development as outlined in the current version of the Queensland Acid Sulphate Sods Technical Manual Soil Management Guidelines 3 The disturbance to the bed and banks of the waterway 1s to be kept to a minimum 4 Ifas a result of any works, any bank 1s displaced the perntit holder shall restore the bank to tts original 5 All construcbon works on the jetty are to occur during times which would minimise sediment and contammmant dispersal 6 All excavated matenal shall be transported to an appropnate location outside of the Coastal Management Distnet 7 Any material or any debris that falls or 1s deposited outside of the alignment of the works shown on the approved plans must be removed within 48 hours following placement of the matenal 8 All temporary works associated with the construction of the works are to be removed from the site at the completion of the works 9 All wastes shall be collected and disposed of at an appropnate lawful facility Water Quality 10 Construction of the works are to be carned out only by means of surtable plant and equipment and measures are to be taken to limit turbedity in tidal waters as a result of the construction 11 All reasonable and practicable measures must be taken to prevent pollution of the waterway as a result of silt run-off, oil and grease spills from machinery, concrete truck washout and alike Wastewater from cleaning equipment must not be discharged chrectly or in-directly to any watercourses 12 If there are any signs of sediment loss, a filter fence or other erosion device to contain sediment contaminated water and prevent contaminabon of tidal waters, is to be installed and maintained until completion of the works Stormwater 13 Stormwater drainage systems are to be constructed to include quality improvement devices (sediment removal, gross pollutant traps) to ensure that stormwater can be effectvely managed and discharged without causing adverse impact on the wetlands adjoining the subject land Compistion 14 Within ten (10) days following completion of the works, notify the DERM so that an inspection can be undertaken to ensure that disturbed areas have been reinstated, are clear of all debns and significant sedimentation has not occurred outside of the construction footprint Page 2 of 4 Department of Environment and Resource Management Page 11 of 13
Page 12
Page 12 of 13 [OCR of page images] Concurrence agency response DERM Permit number: IPCC01683209 Demolition 15 All demolition matenals that are to be removed shall be transported to an appropnate location outside of the Coastal Management Drstnct or other approved location GGL Ben Sale Delegate Department of Environment and Resource Management ae Oy [624 Page 3 of 4 Department of Environment and Resource Management Page 12 of 13
Page 13
Page 13 of 13 [OCR of page images] Concurrence agency response DERM Permit number: IPCC01683209 DEFINITIONS Words and phrases used throughout ths permit’ are defined below ‘Where a definition for a term used in this permet! is sought and the term 1S not defined wathun this permet the definibons prowded in the relevant legislabon shail be used “administering authonty” means the DERM or mts successor I" means Nobee of pene n oF ‘noboe of under the infagrated Planning “approval Act 1997 “approved plans” means the plans and documents isted m the approved plans secon m the notice attached to tus concurrence response “artfhcral waterway” meane an arbficial channel, lake or other body of water Artifical waterway includes — * an artifical channel that 1 formed because the land has been reclaimed from bdal water and 1s intended to allow boahng access to allotments on subdivided land, * — other artifical channels sutyact to the eb and fow of the nde, and * any addtons of attersbons to an artificial waterway “canal™ means an artical waterway surrendered to the State A canals an artficial waterway connected, of intended to be connected, to (dal water, and from which boating access to the bdal water es not hindered by a lock, wer or similar structure “coastal dune” means a ndge or hillock of sand or other matenal on the coast and bull up by the wind “commercial place” means 3 place used as an office or for business or commercial purposes: “dredge spod™ means matenal taken fram the bed or banks of waters by using dredging equipment or other equipment designed for use in extracton of earthen matenal “dwelling” means any of the following structures or vehicles that & pnnapally used a a residence — * a house, unit, motel, nursing home or other buticing or part of a buriding, * a caravan, mobile home or other vehicle or structure on kand, * a water cram a manna “Department of Environment and Resource Management (DERM)” means the department or agency (whatever called) admenstenng the Coastal Protectan and Management Act 1995 of the Enwronmental Protechon Act 1994 “erosion prone area” means an area declared to De an erosion prone area under secton 70(1) of the Coastal Profecton and Management Act 1995 “high water mark" means Me ordmary high water mark at spnng bdes: “land” in the “land schedule” of thes document means land excluding waters and the atmosphere ons of equivalentisméar as required by legistation “permet” licences, apy cer edmurestered by the DERM and the Queensland Parks and Whidiife “ponded pasture” means a permanent or penodc pondage of water wn which the dominant plant speces are pasture species used for gramng oF harvesting “protected area” means — * a protected area under the Nature Conservation Act 1992, or * amanne park under the Marne Parks Act 1992, or * a World Hentage Area. “quarry material” means matenal on State coastal land, other than a mineral within the meaning of any Act relating to mining Matenal includes for example stone, gravel, sand, rock, clay, mud, sit and soll, unless # ss removed from a cuivert, stormwater drain or other dranage infrastructure as waste maternal “site means land or bdal weters on or in which @ 1s proposed to carry out the development approved under this development approval “watercourse” means a river, creek or stream mn wench waler flows parmanenty or intermittently- * mm anatural chamel, whether artificially improved or not, or * man artfaal channel that has changed the course of the watercourse “waters” includes nver, stream, lake, lagoon, pond, swamp, wetland, unconfined surface water, unconfined water nabural or artical watercourse, bed and bank of any waters, dams, non-bdal or bdal waters (inclucing the sea), stormwater channel, stormwater drain, roadside gutter, stormwater run-off, and groundwater and ary part-thereof “waterway” includes a nver, creek, stream, watercourse or inet of the sea “works” or “operation” means the development approved under tvs Gevelopment approval “you” means the holder of this development approval or owner / occupier of the land wich es the subject of tus development approval END OF CONDITIONS Page 4 of 4 Department of Environment and Resource Management Page 13 of 13
Used in these records
Recommendation - Noosa Iconic Panel - 010.2009.00000982.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 380 KB (small file)
- File type
No other editions are linked here.