Council archive · source document
Appendix G - Code Responses · MCU23/0070
EARTHWORKS CODE
Performance outcomes Acceptable Outcomes Applicant’s Comments
development and future use of the land and putrescible or refuse material, vegetation, acid No fill is anticipated to be required for the
filling or excavation works do not result in the sulfate soils, building or construction material development.
contamination of land. or other material or contaminants.
AO6.2 Complies
The site is not on the contaminated land The site is not listed on a contaminated land
register. register.
Haulage activity and amenity
PO7
Haulage of material to and from a site No acceptable outcome provided Complies
ensures— Haul routes from trucks used to transport
material to and from the site will only use major
1. minimal disturbance to
roads as required.
neighbouring properties and
properties along the haulage route;
and
2. Council’s road infrastructure
including pavements is not
adversely affected.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix G - Code Responses.pdfRelated documentApplication case desk ↗
About this file
- File size
- 634 KB (small file)
- File type
No other editions are linked here.