Attachment 1A - ChangeExistingApproval-132005 1550 03 - Stage 1
Attached to the e-mail MCU16/0075 Development Application - 90 Beach Road Noosa North Shore.
ecoaccess
environmonie! licances and permits
i, Proposed actions to Prevent a recurrence of the emergency or incident; and
ii. Outcomes of actions taken at the time to prevent or minimise environmental harm.
(A13-4) As soon as practicable, but not more than six weeks following the conduct of any environmental
monitoring performed in relation to the emergency or incident that results in the release of
contaminants not in accordance, or reasonably expected to be not in accordance with the
conditions of this permit, the holder of the permit must provide written advice of the results of any
such monitoring performed to the administering authority.
END OF CONDITIONS FOR SCHEDULE A
Schedule B - Air
Nuisance
(81-1) The release of noxious or offensive odours or any other noxious or offensive airborne
contaminants resulting from the activity must not cause a nuisance at any odour sensitive place.
Dust nuisance
{B2-1) __- The release of dust and/or particulate matter resulting from the activity must not cause an
environmental nuisance at any dust sensitive place.
(B2-2) Excedence of any of the following levels when measured at any dust sensitive place is an
environmental! nuisance for the purposes of condition B2-1.
i. Dust deposition of 120 milligrams per square metre per day, when monitored in accordance
with Australian Standard AS 3580.10 of 1991; OR
ii. | A concentration of particulate matter with an aerodynamic diameter of less than 10
micrometre (um) (PM10) suspended in the atmosphere of 150 micrograms per cubic metre
over a 24 hour averaging time, at a dust sensitive place downwind of the site, when
monitored in accordance with:
- Australian Standard AS 3580.9.6 ‘Ambient air - Particulate matter - Determination of
suspended particulate PM10 high-volume sampler with size-selective inlet - Gravimetric
method’; or
- Any alternative method of monitoring PM10 which may be permitted by the ‘Air Quality
. Sampling Manual’ as published from time to time by the administering authority.
(B2-3) When requested by the Administering Authority, dust and particulate monitoring must be
undertaken to investigate any complaint of environmental nuisance caused by dust and/or
particulate matter, and the results notified within .14. days to the administering authority following
completion of monitoring. Monitoring must be carried out at a place(s) relevant to the potentially
affected dust sensitive place and at upwind contro! sites and must include:
- Fora complaint alleging dust nuisance, dust deposition; and
- Fora complaint alleging adverse health effects caused by dust, the concentration per cubic
metre of particulate matter with an aerodynamic diameter of less than 10 micrometre (um)
(PM10) suspended in the atmosphere over a 24hr averaging time.
END OF CONDITIONS FOR SCHEDULE B
* Permit includes licences, permits, permits, authorisations, certificates, sanctions Page 8 of 24
or equivalent/similar as required by legislation administered by the
Environmentat Protection Agency and the Queensland Parks and Wildlife Service
Environmental Protection Agency Queensiond| Government
www.epa.gid.gov.ay sen ares tse ron Sutncneamel oes focaection agency
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.