Skip to the record
The gold standard in government transparency.

Original source · versioned page text

2017-11-13 General Committee Meeting Notes

of 22

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  13 NOVEMBER 2017



GENERAL COMMITTEE MEETING - LIVE RECORD MEETING NOTES
13 NOVEMBER 2017 – Crs. Frank Wilkie (Chair), Jess Glasgow, Ingrid Jackson,
Joe Jurisevic, Frank Pardon, Brian Stockwell and Tony Wellington.


1   AMENDMENTS TO THE NOOSA PLAN 2006
    Refer to further report provided at Item 4.


2   REC17/0011 – DEVELOPMENT PERMIT FOR RECONFIGURING A LOT (2 LOTS INTO
    21 LOTS) AT 29 AND 35A TAIT STREET AND 20 EAGLE DRIVE, TEWANTIN
    Committee Recommendation
    Moved:                Cr Wellington
    Seconded:             Cr Pardon
    That Council note the report by the Coordinator Planning to the Planning & Environment
    Committee Meeting dated 7 November 2017 regarding Application No. REC17/0011 for a
    Development Permit to Reconfigure a Lot - 2 Lots into 21 Lots situated at 29 & 35A Tait
    Street, and 14 & 18 Eagle Drive, Tewantin and approve the application in accordance with
    the following conditions:
    Approved Plans
    1.    Development undertaken in accordance with this approval must generally comply with
          the approved plans of development. The approved plans are listed in the following table
          unless otherwise amended by these conditions.
               Plan No.      Rev.    Plan/Document Name                         Date
               1702          A       Eagle Drive – Tewantin                 18.10.2017
                                     Detailed Lot Layout prepared by Haynes
                                     Consulting Engineers
    2.    The north-eastern corner of proposed Lot 15 and the south-eastern corner of proposed
          Lot 12 must be truncated to provide a minimum 3.5m wide verge from the new kerb
          line. The truncations must be created with 3 chords.
    New Road
    3.    The new road (extension of Eagle Drive) shown on the Approved Plans must be
          constructed in accordance with the conditions of this Decision Notice and dedicated as
          road reserve at no cost to Council.
    4.    The works must be undertaken in accordance with an Operational Works approval and
          must include in particular:
          a.      an “access” road in accordance with Council’s Planning Scheme Policy 5 –
                  Engineer Design Standards – Roads, Drainage and Earthworks (reserve width
                  of 15 metres minimum and a carriageway width of 6 metres kerb to kerb)
          b.      sealing, drainage, kerbing and channelling
          c.      construction of pedestrian footpaths as shown on the approved plans
          d.      installation of street lighting

                                                                                   Page 1 of 22
Log in to download the original file

2017-11-13 General Committee Meeting Notes(PDF, 692KB).pdf · 708 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 21 sections

Section 2

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                     13 NOVEMBER 2017


    5.    The new road must terminate in a cul-de-sac with a circular turning area of sufficient
          size to accommodate the single forward motion turn of a Waste Collection Vehicle
          (WCV) clear of private driveways on-street parking and speed control devices or if the
          adjoining property to the east (No 28 Elkhorn Drive - Lot 70 M37807) has been
          developed the “access” road formation must extend to and match smoothly with the
          existing formation within Lot 70 M37807, whichever is applicable at the time of
          construction.
    External Works
    6.    Access to proposed Lots 7 and 8 must be from the Road 86419 frontage only (northern
          boundary) and the approved plans amended accordingly. The works must be
          undertaken in accordance with an Operational Works approval and must be
          constructed prior to the sealing of the survey plan. The works must include in particular:
          a.    a half road construction consisting of 3m wide seal, kerbing and channelling and
                extending from the Tait Street formation for a distance of 40 metres from Tait
                Street (western boundary of Lot 6) terminating in a temporary turnaround;to the
                eastern boundary of proposed Lot 8
          b.    the intersection with Tait Street;
          c.    the northern half of the new road constructed with a gravel formation;
          d.    the realignment of the existing vehicle track to join to the end of the southern half
                of the new road;
          e.    the removal of the redundant sections of the existing vehicle track and the areas
                turfed or grass seeded;
          f.    the construction of the vehicle access to proposed Lots 7 and 8.
    Stormwater Quantity
    7.    The new stormwater works must be constructed in accordance with the approved plans
          and the works must be undertaken in accordance with an Operational Works approval.
    8.    The stormwater elements of the development, including the basin at 14 Eagle Drive,
          are to be built in accordance with the BSM stormwater report Detailed Design of
          Stormwater Detention Volume dated 18.09.2017, letter from BSM dated 13.10.2017,
          letter from Haynes Consulting Engineers dated 11.10.2017 and accompanying plans.
          Where design elements will be finalised at a later stage, these will be in accordance
          with the relevant codes, standards, guidelines and Council’s requirements.
    9.    All basin retaining structures are to be structurally certified to Council’s design life as
          part of operational works design and certification is to be provided to Council prior to
          plan sealing.
    10.   Appropriate protection will be provided against scour at basin inflow and outflow points.
    Stormwater Quality
    11.   Prior to Council accepting water quality treatment device assets “Off Maintenance”, the
          applicant must provide Council with a Schedule of Maintenance Costs for all activities
          undertaken to maintain the bio retention basins in accordance with the most current
          version of Healthy Waterways Bio-retention Basin Maintaining Vegetated Stormwater
          Assets Guidelines. The schedule shall include records of actual costs of maintenance
          work undertaken.



                                                                                       Page 2 of 22

Section 3

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                    13 NOVEMBER 2017


    Vegetation
    12.   Existing native trees on the site and in the road verge must be retained in accordance
          with an Arborist Report for the development and referenced in a Development Permit
          for Operational Works. The existing native trees to be retained must be located clear
          of proposed services, not present a nuisance to neighbouring properties and generally
          suitable for the proposed location.
    13.   Vegetation must only be removed or disturbed in accordance with a Fauna
          Management Plan (or part thereof) and endorsed through an Operational Works
          approval.
    Landscaping Works
    14.   The development site must be landscaped. The works must be undertaken in
          accordance with an Operational Works approval and the Noosa Plan for that specific
          area and must include in particular:
          a.     Provision of 1 native street tree within the road reserve for every 8 metres of new
                 road.
          b.     100mm deep mulching and landscaping to any batter within road reserves that
                 exceed 1 in 4 slope (25%).
          c.     Turf and garden beds to road reserve, including retained trees.
          d.     Retaining walls within the bio-basin must be constructed or permanently faced
                 with materials which provide for a natural appearance such as sandstone,
                 bluestone, granite or the like.
          e.     Removal of all weeds species listed in the following standards and legislation.
                 i.    3.4.1.declared plants under the Land Protection (Pest and Stock Route
                       Management) Act 2002 and sub-ordinate Regulation 2003.
                 ii.   3.4.2.The Noosa Local Government Area Pest Management Plan 2015-
                       2019
    15.   All landscape works must be established and maintained in accordance with
          horticultural best practice with construction techniques that allow for healthy, sustained
          and vigorous plant growth. All plant material must be allowed to grow to full form.
    16.   All entry statements, fences, batters, retaining walls and buffer/screen plantings must
          be located entirely within private land and not within the public road reserve.
    17.   All landscape works must be maintained generally in accordance with the approved
          design for the life of the development.
          Estate Entrance Feature
    18.   Any proposed estate entrance feature must:
          a.     reflect a subdued local character, rather than an overbearing or contrived
                 statement
          b.     comprise feature vegetation (either existing or planted) in preference to built
                 forms
          c.     integrate with the landscape design of the balance of the estate
          d.     be constructed of durable and low maintenance materials
          e.     be treated with a graffiti resistant coating

                                                                                      Page 3 of 22

Section 4

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  13 NOVEMBER 2017


          f.    not restrict pedestrian access
          Any estate entrance works must be undertaken in accordance with an Operational
          Works approval.
    Property Access and Driveways
    19.   A residential driveway must be constructed to each lot. The works must be undertaken
          in accordance with an Operational Works approval.
    20.   The access driveways to service Lots 8, 20 and 21 must extend for the full length of
          the access handle. The works must be undertaken in accordance with an Operational
          Works approval.
    21.   Vehicle access to Lots 7 & 8 is are limited to the Road 86419 frontage only (northern
          boundary). A clause must be included in the contract of sale for Lots 7 & 8 which
          prohibits vehicle access being taken from Eagle Drive.
    Pedestrian and Bicycle Facilities
    22.   Pedestrian and bicycle facilities must be provided for the development. The works must
          be undertaken in accordance with an Operational Works approval and must include in
          particular:
          a.    A 2 metre wide footpath within the road verge for the entire length shown on the
                approved plans.
          b.    A 1.5 metre wide footpath must be provided on the northern side of the bio-basin
                extending from Eagle Drive to Clarey Park and a pool fence must be provided
                between the footpath and the bio-basin
    Electricity and Telecommunication Services
    23.   Underground reticulated electricity and telecommunication services must be provided
          to each lot in accordance with an approval for Operational Works and the standards
          and requirements of the relevant service provider.
    24.   Unless otherwise stipulated by telecommunications legislation at the time of
          construction, the development must be provided with all necessary conduits, pits and
          pipes to accommodate the future connection of optic fibre technology
          telecommunications.
    25.   Certification must be submitted to Council from all relevant service providers which
          certifies that the development has met the requirements of this Decision Notice and all
          applicable legislation at the time of construction.
    Easements
    26.   A minimum 1.5 metre wide easement for drainage purposes must be registered against
          the title/s of the burdened properties in favour of the benefitted properties over the
          proposed easements identified on the Approved Plans. The easements must of
          sufficient width to wholly encompass the drainage structures and the associated
          overland flowpaths.
    27.   An easement for access and service purposes must be registered against the titles of
          proposed Lot 21 in favour of proposed Lot 20
    28.   Unless otherwise agreed in writing by the relevant service provider, any public or third
          party infrastructure located on the subject site must be placed within an easement
          registered against the title of the property.


                                                                                    Page 4 of 22

Section 5

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   13 NOVEMBER 2017


    29.   All easements must be designed in accordance with the planning scheme and granted
          at no cost to the Grantee. Where the Grantee is Council or a service authority, the
          easement documentation must be in accordance with the Grantee’s standard
          easement terms. Draft easement documentation must be submitted to Council for
          endorsement.
    30.   All works must be kept clear of any existing or proposed easements on the subject
          land, unless agreed otherwise in writing by the Grantee.
    Earthworks and Retaining Walls
    31.   All fill and associated batters must be undertaken in accordance with an Operational
          Works approval, and contained entirely within the subject site unless written permission
          from the respective landowner(s) is provided to Council.
    32.   All fill and associated batters must be contained entirely within the subject site unless
          written permission from the respective landowner(s) is provided to Council. All
          earthworks must be undertaken in accordance with the provisions of Australian
          Standard AS3798: Guidelines on Earthworks for Commercial and Residential
          Developments.
                                                                                           Carried.


3   132005.220.05 & OPW12/0031.02 – APPLICATION FOR EXTENSION TO CURRENCY
    PERIOD FOR A PRELIM. APPROVAL TO OVERRIDE PLANNING SCHEME,
    DEVELOPMENT PERMIT TO RECONFIGURE A LOT & DEVELOPMENT PERMIT FOR
    OPERATIONAL WORKS AT 70 CARPENTERS RD & 25 JARRAH ST, COOROY
    Motion
    Moved:            Cr Stockwell
    Seconded:         Cr Jackson
    That Council note the report by the Development Planner to the Planning & Environment
    Committee Meeting dated 7 November 2017 regarding Application No. 132005.220.05 &
    OPW12/0031.2 for an extension to the currency period for a Preliminary Approval to Override
    the Planning Scheme (22 Village Industry lots), Development Permit to Reconfigure a Lot
    (22 Village Industry Lots, a Balance Lot, Drainage Reserve & Park Lots) and a Development
    Permit for Operational Works - Extension to Currency Period, situated at 70 Carpenters Road
    and 25 Jarrah Street, Cooroy and:
    A.    Approve a change to Condition 11 of approval 132005.220.05 to read as follows:
          11.   The Preliminary Approval to Override the Planning Scheme and Development
                Permit for Reconfiguring a Lot lapses if the works have not been completed by 8
                October 20212019, unless an application to extend the currency period is
                approved by Council.
    B.    Approve an amendment to section 3 of approval OPW12/0031.02 to read as follows:
          “The currency period for this development approval is until 8 October 2021 2019 during
          which time all works must be completed unless an application to extend the relevant
          period is approved by Council.”
    C.    Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.



                                                                                     Page 5 of 22

Section 6

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                13 NOVEMBER 2017


    Amendment
    Moved:           Cr Pardon
    Seconded:        Cr Wellington
    That the motion be amended to change the date of the currency period for the preliminary
    approval and development approval to 8 October 2021.
                                                                                      Carried.
    Committee Recommendation
    Moved:           Cr Stockwell
    Seconded:        Cr Jackson
    That Council note the report by the Development Planner to the Planning & Environment
    Committee Meeting dated 7 November 2017 regarding Application No. 132005.220.05 &
    OPW12/0031.2 for an extension to the currency period for a Preliminary Approval to Override
    the Planning Scheme (22 Village Industry lots), Development Permit to Reconfigure a Lot
    (22 Village Industry Lots, a Balance Lot, Drainage Reserve & Park Lots) and a Development
    Permit for Operational Works - Extension to Currency Period, situated at 70 Carpenters Road
    and 25 Jarrah Street, Cooroy and:
    A.   Approve a change to Condition 11 of approval 132005.220.05 to read as follows:
         11.    The Preliminary Approval to Override the Planning Scheme and Development
                Permit for Reconfiguring a Lot lapses if the works have not been completed by 8
                October 2021, unless an application to extend the currency period is approved
                by Council.
    B.   Approve an amendment to section 3 of approval OPW12/0031.02 to read as follows:
         “The currency period for this development approval is until 8 October 2021 during
         which time all works must be completed unless an application to extend the relevant
         period is approved by Council.”
    C.   Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
                                                                                      Carried.


4   FURTHER REPORT – AMENDMENTS TO THE NOOSA PLAN 2006
    Committee Recommendation
    Moved:           Cr Stockwell
    Seconded:        Cr Jackson
    That Council note the reports by the Planning Scheme Project Manager to the Planning &
    Environment Committee dated 7 November 2017 and the General Committee Meeting dated
    13 November 2017, and:
    A.   Resolve under section 18 of the Planning Act 2016 to amend The Noosa Plan 2006 by
         introducing new provisions for Multiple Housing Type 2 Duplex and correcting minor
         errors and inconsistencies in accordance with Attachment 1 of the report by the
         Planning Scheme Project Manager dated 7 November 2017;
    B.   Authorise the Chief Executive Officer to:
         1.     Forward the proposed amendments to the Minister for state interest review;

                                                                                 Page 6 of 22

Section 7

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


         2.     Undertake public consultation and review submissions; and
         3.     Subject to submissions not raising material issues, adopt the proposed
                amendments and place a public notice in the government gazette; and
    C.   Resolve to amend The Noosa Plan 2006 under the Alignment Amendment Rules made
         by the Planning Minister under section 293 of the Planning Act 2016, as outlined in
         Attachment 2 of the report by the Planning Scheme Project Manager dated 7
         November 2017, and authorise the Chief Executive Officer to effect the amendments.
                                                                                       Carried.


5   MCU17/0054 - DEVELOPMENT PERMIT FOR MATERIAL CHANGE OF USE OF
    PREMISES - RETAIL BUSINESS TYPE 2 - SHOP, SALON & ENTERTAINMENT & DINING
    BUSINESS TYPE 1 - FOOD & BEVERAGES AT 11 - 19 HILTON TERRACE, TEWANTIN
    Motion
    Moved:              Cr Wellington
    Seconded:           Cr Pardon
    That Council note the report by the Coordinator Planning to the General Committee Meeting
    dated 13 November 2017, regarding Application No. MCU17/0054 for a Development Permit
    for Material Change of Use of Premises - Retail Business Type 2 - Shop & Salon and
    Entertainment & Dining Business Type 1 - Food & Beverages, situated at 11 – 19 Hilton
    Terrace, Tewantin and:
    A.   Approve the application subject to the following conditions
         1.     Development undertaken in accordance with this approval must generally comply
                with the approved plans of development. The approved plans are listed in the
                following table unless otherwise amended by these conditions.
                     Plan No.        Rev.   Plan/Document Name                        Date
                     DA-07.1216.2D   D      Site Plan/Floor Plan prepared by Andrew   14.06.2017
                                            McKellar Design
                     DA-07.1216.3D   D      Roof plan prepared by Andrew McKellar     14.06.2017
                                            Design
                     DA-07.1216.4D   D      Elevations prepared by Andrew McKellar    14.06.2017
                                            Design
                     DA-07.1216.5D   D      Sections prepared by Andrew McKellar      June 2017
                                            Design
                     DA-07.1216.6D   D      Sections prepared by Andrew McKellar      June
                                            Design

                Nature and Extent of Approved Use
         2.     The approved use must not operate outside the hours of:
                a.      6am to 10pm Monday to Thursday
                b.      6am to 12pam Friday and Saturday
                c.      6am to 10pm Sunday or any public holiday
                The requirements of this condition must be included in the Community
                Management Statement for any body corporate for the subject site.

                                                                                  Page 7 of 22

Section 8

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   13 NOVEMBER 2017


        3.    The outdoor dining areas must not exceed 30m2 and 35m2 as shown on the
              approved plans and must not be used after 10pm each night.
        4.    The approved uses must not cause nuisance as a result of noise emission.
        5.    Entertainers or speakers used to amplify noise must not be located in any
              outdoor, verandah, patio, footpath or beer garden area of the premises.
              Building Appearance
        6.    Ground floor shopfront glazing along the frontages must be fully transparent to a
              minimum of 6550% of the street frontage to allow passive surveillance and
              encourage social interaction, and must be provided at full height (floor to ceiling).
        7.    The external finishes of the building must include a mix of materials, variation in
              roof form and extensive eaves as shown on the Approved Plans.
        8.    All mechanical equipment and other service infrastructure located on the site
              must be:
              a.    located not less than 2 metres from a property boundary
              b.    fully enclosed or screened such that they are not visible from the street
                    frontages nor adjoining properties. Where screened by landscaping,
                    landscaping beds must be at least 1.5 metres wide.
              Soil Contamination
        9.    As part of any Operational Works application for the site a detailed site
              contamination assessment report prepared by a suitably qualified and
              experienced person in accordance with the procedures and practices detailed in
              the National Environment Protection (Assessment of Site Contamination)
              Measure 1999 (NEPM) is required. The report must conclude:
              a.    whether the site is suitable for the proposed new use/development (with
                    and without remediation and/or management);
              b.    whether any site contamination is causing, or is likely to cause,
                    ‘environmental harm’ (as defined under the Environmental Management
                    and Pollution Control Act 1994); and
              c.    whether any site contamination presents an occupational health and safety
                    risk to workers involved in redevelopment of the site.
        10.   If the site contamination assessment report concludes that remediation and/or
              management strategies are necessary to avoid risks to human health or the
              environment, a proposed remediation and/or management plan must be
              submitted to Council prior to the commencement of building works. Any
              remediation or management plan involving soil disturbance must include a
              detailed soil and water management plan to prevent off-site transfer of
              potentially-contaminated soil or stormwater.
              NB: It is mandatory for any contaminated land investigation documents, including
              investigation reports, validation reports and draft site management plans to be
              certified by an approved auditor and must have approval from the Department of
              Environment and Heritage and Protection (DEHP). DEHP have list of approved
              auditors.




                                                                                    Page 8 of 22

Section 9

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


              Site Access and Driveways
        11.   A sealed access driveway must be provided from Ernest Street and Earl Street
              to all parking and manoeuvring areas of the development. The works must be
              undertaken in accordance with an Operational Works approval and must include
              in particular:
              a.    driveway crossovers in accordance with Council’s standard drawing RS-
                    051
              b.    suitable safety measures, including warning signage, to improve driver
                    awareness of pedestrians and enhance pedestrian safety. Warning
                    signage must be provided near the driveways to warn motorists of
                    pedestrian movement along the street frontages
        12.   All vehicles must enter and leave the site in a forward direction.
              Car Parking
        13.   A minimum of 38 car parking spaces must be provided and marked on the site
              and made available and accessible at all times while the use is open for business.
              The works must be undertaken in accordance with an Operational Works
              approval and must include in particular:
              a.    pedestrian routes in accordance with the approved plans
              b.    provision of vandal resistant public lighting with intensities to satisfy the
                    requirements of Australian Standard AS1158: Public Lighting Code
              c.    1 disabled parking space/s within the total
              d.    dimensions, crossfalls and gradients in accordance with Australian
                    Standard AS2890: Parking Facilities
        14.   All car parking areas and access driveways must be maintained exclusively for
              vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
        15.   Directional signage must be provided to direct visitors and customers to the car
              parking spaces provided on site.
              Service Vehicles
        16.   Service vehicle parking, manoeuvring and standing spaces must be provided on
              the site. The works must be undertaken in accordance with an Operational Works
              approval and must include in particular:
              a.    regular access for a Waste Collection Vehicle
        17.   Service vehicle movements associated with the approved use (including loading
              and unloading) must not occur outside the hours of 6am to 6pm Monday to
              Saturday and not at all on Sundays or public holidays. The requirements of this
              condition must be included in the Community Management Statement for any
              body corporate for the subject site.
              Pedestrian and Bicycle Facilities
        18.   Pedestrian and bicycle facilities must be provided for the development. The
              works must be undertaken in accordance with an Operational Works approval
              and must include in particular:
              a.    Internal pedestrian footpaths in accordance with the approved plans


                                                                                   Page 9 of 22

Section 10

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


              b.    a total of 12 bicycle parking spaces
              c.    end of trip facilities involving 12 lockers, 1 male and female shower and
                    change rooms.
              Public Safety
        19.   All ground floor shopfront glazing must be protected against vandalism by the
              use of a form of safety glass such as toughened or laminated glass.
        20.   During operating hours, all parking areas, pedestrian areas and entrances/exits
              to all stairwells, foyers and public toilets must be well lit with vandal resistant
              lighting and with intensities to satisfy the requirements of Australian Standard
              AS1158 “Public Lighting Code”. Lighting must be designed to reduce the contrast
              between shadows and well lit areas. In particular, appropriate security lighting
              must be provided in the location shown at the corridor servicing the toilets and
              change room.
              Electricity and Telecommunication Services
        21.   Unless otherwise stipulated by telecommunications legislation at the time of
              construction, the development must be provided with all necessary conduits, pits
              and pipes to accommodate the future connection of optic fibre technology
              telecommunications.
        22.   Certification must be submitted to Council from all relevant service providers
              which certifies that the development has met the requirements of this Decision
              Notice and all applicable legislation at the time of construction.
              Easements
        23.   Unless otherwise agreed in writing by the relevant service provider, any public or
              third party infrastructure located on the subject site must be placed within an
              easement registered against the title of the property.
        24.   All easements must be designed in accordance with the planning scheme and
              granted at no cost to the Grantee. Where the Grantee is Council or a service
              authority, the easement documentation must be in accordance with the Grantee’s
              standard easement terms. Draft easement documentation must be submitted to
              Council for endorsement.
        25.   All works must be kept clear of any existing or proposed easements on the
              subject land, unless agreed otherwise in writing by the Grantee.
              Earthworks and Retaining Walls
        26.   All fill and associated batters must be undertaken in accordance with an
              Operational Works approval, and contained entirely within the subject site unless
              written permission from the respective landowner(s) is provided to Council.
        27.   All retaining walls must be designed and constructed in accordance with the
              planning scheme and must be certified by an RPEQ where exceeding 1.0m in
              height. All retaining walls that are publicly accessible and exceed 1.0m in height
              must be fitted with a commercial grade safety fence.
              Damage to Services and Assets
        28.   Any damage caused to existing services and assets as a result of the
              development works must be repaired at no cost to the asset owner at the
              following times:

                                                                                 Page 10 of 22

Section 11

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


              a.    where the damage would cause a hazard to pedestrian or vehicle safety,
                    immediately; or
              b.    where otherwise, upon completion of the works associated with the
                    development.
              Any repair work which proposes to alter the alignment or level of existing services
              and assets must first be referred to the relevant service authority for approval.
              Landscaping Works
        29.   The development site must be landscaped prior to the commencement of use.
              The works must be undertaken in accordance with an Operational Works
              approval and the Noosa Plan for that specific area and must include in particular:
              a.    the landscape areas shown on the approved Site Plan/Floor Plan prepared
                    by Andrew McKellar Design dated 14.06.2017.
              b.    a minimum 2-metre-wide landscaping strip along the Ernest and Hilton road
                    frontage of the subject site, exclusive of the access driveway, generally
                    uncompromised by infrastructure items.
              c.    Any retaining walls must be setback from the front boundaries as shown
                    on the Approved Plans and screened with landscaping. Landscaping plans
                    must clearly show any retaining structure and adequately demonstrate how
                    these structures will be permanently screened with native vegetation.
              d.    all letterboxes located inside the development or in a position which does
                    not visually dominate the frontage.
              e.    details of the rendered wall finish on the Hilton terrace frontage, which can
                    include stone facing or other natural looking finishes and complement the
                    proposed landscaping.
              f.    sub-terrain tree planting area demonstrating at least 4m³ area of structured
                    soils per tree is available for root growth and is not subject to compaction.
              g.    Provision of 100L Melaleuca quinquenervia along the frontage.
              h.    Details and depths of all landscaping soils, especially where subject to
                    compaction relating to filling of the site.
              i.    Plant selection generally as shown on the landscape documentation.
              j.    Bio-basin landscape plants must include a mixture of at least five of the
                    following species for planting in the bio-retention basin extended detention
                    surface at a minimum density of 8 plants/m²:
                    i.     Carex appressa
                    ii.    Carex fascicularis
                    iii.   Ficinia nodosa
                    iv.    Juncus usitatis
                    v.     Lomandra longifolia
                    vi.    Ghania sieberiana
        30.   All landscape works must be established and maintained in accordance with the
              approved design for the life of the development, and in a manner that ensures
              healthy, sustained and vigorous plant growth. All plant material must be allowed
              to grow to full form and be refurbished when its life expectancy is reached.

                                                                                  Page 11 of 22

Section 12

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                               13 NOVEMBER 2017


        31.   All landscape works must be maintained generally in accordance with the
              approved design for the life of the development.
              Stormwater Drainage
        32.   The site must be provided with a stormwater drainage system connecting to a
              lawful point of discharge. The works must be undertaken in accordance with an
              Operational Works approval and be generally in accordance with the submitted
              Stormwater Management Plan - Revision A dated 19 April 2017, prepared by
              Switchback 48 Consulting.
        33.   Stormwater runoff from the development must be disposed of on-site without
              causing scour or damage to the subject site or any adjoining property. Plans
              submitted for the Operational Works approval must include calculations in
              accordance with Queensland Urban Drainage Manual for any overland flow
              discharge areas to confirm that scour will not result from the development.
        34.   A stormwater quality treatment system must be provided for the development.
              The works must be undertaken in accordance with an Operational Works
              approval and the Bio-retention Technical Design Guidelines (Water by Design,
              2012), and must include in particular:
              a.   stormwater quality treatment devices of a size and location of 30m2 plus
                   25m2 generally in accordance with those shown in section 2 of the of the
                   Stormwater Management Plan for 11-19 Hilton Terrace Tewantin by
                   Switchback Consulting, dated 19 April 2017.
              b.   Bio-retention devices which:
                   i.     are designed generally in accordance with the Water by Design
                          Technical Design Guidelines for bio-retention basins
                   ii.    are provided with a free-draining outlet from the sub-soil drainage
                          system
                   iii.   swales which are designed in accordance with the Water Sensitive
                          Urban Design Technical Design Guidelines for South East
                          Queensland
                   iv.    have batters around the entire perimeter, or where demonstrated that
                          is not feasible, have retaining structures only of the maximum size
                          recommended within the Water by Design Technical Design
                          Guidelines for bio-retention basins.
        35.   All stormwater quality treatment devices must be maintained in accordance with
              the Water by Design (2009) - Maintaining Vegetated Stormwater Assets (Version
              1). A copy of this document must be retained on the site together with the
              approved Operational Works drawings for the stormwater quality treatment
              system and a detailed life cycle costing of the system attached as an addendum.
              Records of all maintenance activities undertaken must be kept and made
              available to Council upon request.
        36.   Any proposed Community Management Statement required for the development
              must include the Water by Design (2009) – Maintaining Vegetated Stormwater
              Assets (Version 1) document and must include the full cost of maintaining the
              system in accordance with that document.



                                                                               Page 12 of 22

Section 13

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                   13 NOVEMBER 2017


        37.   The applicant must submit plans for approval with the operational works
              application for the inclusion of educational signage or stencilling to be
              incorporated within the development to ensure patrons are reminded to minimise
              waste and place it in bins.
              Stormwater Harvesting
        38.   Operating underground stormwater harvesting tanks must be provided for the
              development. The tanks must be provided in accordance with an Operational
              Works approval and must include in particular:
              a.    a total tank capacity of a size suitable to maintain expected non-potable
                    and outdoor uses for a 2 month period without rain.
              b.    a minimum catchment of 50% of the building roof area.
              c.    re-use of harvested rainwater for internal non-potable uses and outdoor
                    uses.
              d.    stormwater harvesting tanks are to be located to the rear of the building.
        39.   Certification must be submitted to Council from a qualified person which certifies
              that the rainwater collection tank/s and associated reticulation has/have been
              installed in accordance with the requirements of this Decision Notice.
              Acid Sulfate Soils
        40.   All works must be carried out in accordance with an Acid Sulfate Soil and
              Groundwater Management Plan for the development prepared by a suitably
              qualified person and referenced in a Development Permit for Operational Works.
              The Acid Sulfate Soil and Groundwater Management Plan submitted with the
              application for Operational Works must detail:
              a.    Management necessary for the proposed filling to avoid any impacts of the
                    Potential Acid Sulfate Soils identified on the site – in particular impacts
                    related to compacting Acid Sulfate Soils into the groundwater table and
                    releasing water contaminants.
              b.    design measures necessary to prevent any oxidation of the potential acid
                    sulfate soils or transfer of acid sulfate soil leachates via dewatering of
                    groundwater through underground pipe bedding material.
              c.    Any other matters necessary to prevent the oxidation of potential acid
                    sulfate soils or release of Acid Sulfate Soil related water contaminants.
        41.   All waters, including stormwater runoff, groundwater seepage and leachate from
              acid sulfate soils must achieve the following quality prior to release from the site:
              a.    a pH range of 6.5-8.5 pH units
              b.    50mg/L maximum total suspended solids concentration
              c.    0.3mg/L maximum total iron concentration
              d.    0.2mg/L maximum total aluminium concentration
              e.    no visible plume at either the point of release from the site or within a
                    waterway




                                                                                   Page 13 of 22

Section 14

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  13 NOVEMBER 2017


                Waste Disposal
         42.    The developer must provide waste storage and disposal facilities in accordance
                with Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and
                Commercial and Industrial Premises”. The facilities must include an external
                impervious area correctly sized for all refuse and recycling containers and
                suitably screened from public places and neighbouring properties. A bin wash
                area is required with a cold-water tap, hose and drain outlet connected to sewer,
                via a bucket trap. The drain outlet must be designed to prevent storm water entry
                to the sewerage system.
         43.    Refuse containers must be provided in accordance with the requirements of the
                Environmental Protection (Interim Waste) Regulation 1996 and (Waste
                Management) Regulation 2000, for the storage and collection of refuse.
         44.    Public bins must be provided throughout the car park to reduce littering. Bins
                provided must be for refuse and recycling and be decanted into the bulk bins by
                the site operators.
    B.   Enter into an Infrastructure Agreement with the applicant that provides for the
         acquisition of part of the site, compensation for this land acquisition, frontage works
         being undertaken by Council, demolishing of the existing building and car parking in
         lieu of 8 on-site car parking spaces.


    Amendment
    Moved:           Cr Stockwell
    Seconded:        Cr Jurisevic
    That condition 7 be amended to read:
    7.   The external finishes of the building must include a mix of materials consistent with the
         Noosa Design Principles with particular attention to the Earl Street façade, and
         variation in roof form and extensive eaves as shown on the Approved Plans.
                                                                                              Lost.

    Committee Recommendation
    Moved:           Cr Wellington
    Seconded:        Cr Pardon
    That Council note the report by the Coordinator Planning to the General Committee Meeting
    dated 13 November 2017, regarding Application No. MCU17/0054 for a Development Permit
    for Material Change of Use of Premises - Retail Business Type 2 - Shop & Salon and
    Entertainment & Dining Business Type 1 - Food & Beverages, situated at 11 – 19 Hilton
    Terrace, Tewantin and:
    A.   Approve the application subject to the following conditions
         1.     Development undertaken in accordance with this approval must generally comply
                with the approved plans of development. The approved plans are listed in the
                following table unless otherwise amended by these conditions.
                  Plan No.          Rev.   Plan/Document Name                          Date
                  DA-07.1216.2D     D      Site Plan/Floor Plan prepared by Andrew     14.06.2017
                                           McKellar Design

                                                                                  Page 14 of 22

Section 15

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                  13 NOVEMBER 2017


                  DA-07.1216.3D   D      Roof plan prepared by Andrew McKellar         14.06.2017
                                         Design
                  DA-07.1216.4D   D      Elevations prepared by Andrew McKellar        14.06.2017
                                         Design
                  DA-07.1216.5D   D      Sections prepared by Andrew McKellar          June 2017
                                         Design
                  DA-07.1216.6D   D      Sections prepared by Andrew McKellar          June
                                         Design

             Nature and Extent of Approved Use
        2.   The approved use must not operate outside the hours of:
             a.      6am to 10pm Monday to Thursday
             b.      6am to 12pam Friday and Saturday
             c.      6am to 10pm Sunday or any public holiday
             The requirements of this condition must be included in the Community
             Management Statement for any body corporate for the subject site.
        3.   The outdoor dining areas must not exceed 30m2 and 35m2 as shown on the
             approved plans and must not be used after 10pm each night.
        4.   The approved uses must not cause nuisance as a result of noise emission.
        5.   Entertainers or speakers used to amplify noise must not be located in any
             outdoor, verandah, patio, footpath or beer garden area of the premises.
             Building Appearance
        6.   Ground floor shopfront glazing along the frontages must be fully transparent to a
             minimum of 6550% of the street frontage to allow passive surveillance and
             encourage social interaction, and must be provided at full height (floor to ceiling).
        7.   The external finishes of the building must include a mix of materials, variation in
             roof form and extensive eaves as shown on the Approved Plans.
        8.   All mechanical equipment and other service infrastructure located on the site
             must be:
             a.      located not less than 2 metres from a property boundary
             b.      fully enclosed or screened such that they are not visible from the street
                     frontages nor adjoining properties. Where screened by landscaping,
                     landscaping beds must be at least 1.5 metres wide.
             Soil Contamination
        9.   As part of any Operational Works application for the site a detailed site
             contamination assessment report prepared by a suitably qualified and
             experienced person in accordance with the procedures and practices detailed in
             the National Environment Protection (Assessment of Site Contamination)
             Measure 1999 (NEPM) is required. The report must conclude:
             a.      whether the site is suitable for the proposed new use/development (with
                     and without remediation and/or management);




                                                                                  Page 15 of 22

Section 16

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


              b.    whether any site contamination is causing, or is likely to cause,
                    ‘environmental harm’ (as defined under the Environmental Management
                    and Pollution Control Act 1994); and
              c.    whether any site contamination presents an occupational health and safety
                    risk to workers involved in redevelopment of the site.
        10.   If the site contamination assessment report concludes that remediation and/or
              management strategies are necessary to avoid risks to human health or the
              environment, a proposed remediation and/or management plan must be
              submitted to Council prior to the commencement of building works. Any
              remediation or management plan involving soil disturbance must include a
              detailed soil and water management plan to prevent off-site transfer of
              potentially-contaminated soil or stormwater.
              NB: It is mandatory for any contaminated land investigation documents, including
              investigation reports, validation reports and draft site management plans to be
              certified by an approved auditor and must have approval from the Department of
              Environment and Heritage and Protection (DEHP). DEHP have list of approved
              auditors.
              Site Access and Driveways
        11.   A sealed access driveway must be provided from Ernest Street and Earl Street
              to all parking and manoeuvring areas of the development. The works must be
              undertaken in accordance with an Operational Works approval and must include
              in particular:
              a.    driveway crossovers in accordance with Council’s standard drawing RS-
                    051
              b.    suitable safety measures, including warning signage, to improve driver
                    awareness of pedestrians and enhance pedestrian safety. Warning
                    signage must be provided near the driveways to warn motorists of
                    pedestrian movement along the street frontages
        12.   All vehicles must enter and leave the site in a forward direction.
              Car Parking
        13.   A minimum of 38 car parking spaces must be provided and marked on the site
              and made available and accessible at all times while the use is open for business.
              The works must be undertaken in accordance with an Operational Works
              approval and must include in particular:
              a.    pedestrian routes in accordance with the approved plans
              b.    provision of vandal resistant public lighting with intensities to satisfy the
                    requirements of Australian Standard AS1158: Public Lighting Code
              c.    1 disabled parking space/s within the total
              d.    dimensions, crossfalls and gradients in accordance with Australian
                    Standard AS2890: Parking Facilities
        14.   All car parking areas and access driveways must be maintained exclusively for
              vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
        15.   Directional signage must be provided to direct visitors and customers to the car
              parking spaces provided on site.

                                                                                   Page 16 of 22

Section 17

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


              Service Vehicles
        16.   Service vehicle parking, manoeuvring and standing spaces must be provided on
              the site. The works must be undertaken in accordance with an Operational Works
              approval and must include in particular:
              a.    regular access for a Waste Collection Vehicle
        17.   Service vehicle movements associated with the approved use (including loading
              and unloading) must not occur outside the hours of 6am to 6pm Monday to
              Saturday and not at all on Sundays or public holidays. The requirements of this
              condition must be included in the Community Management Statement for any
              body corporate for the subject site.
              Pedestrian and Bicycle Facilities
        18.   Pedestrian and bicycle facilities must be provided for the development. The
              works must be undertaken in accordance with an Operational Works approval
              and must include in particular:
              a.    Internal pedestrian footpaths in accordance with the approved plans
              b.    a total of 12 bicycle parking spaces
              c.    end of trip facilities involving 12 lockers, 1 male and female shower and
                    change rooms.
              Public Safety
        19.   All ground floor shopfront glazing must be protected against vandalism by the
              use of a form of safety glass such as toughened or laminated glass.
        20.   During operating hours, all parking areas, pedestrian areas and entrances/exits
              to all stairwells, foyers and public toilets must be well lit with vandal resistant
              lighting and with intensities to satisfy the requirements of Australian Standard
              AS1158 “Public Lighting Code”. Lighting must be designed to reduce the contrast
              between shadows and well lit areas. In particular, appropriate security lighting
              must be provided in the location shown at the corridor servicing the toilets and
              change room.
              Electricity and Telecommunication Services
        21.   Unless otherwise stipulated by telecommunications legislation at the time of
              construction, the development must be provided with all necessary conduits, pits
              and pipes to accommodate the future connection of optic fibre technology
              telecommunications.
        22.   Certification must be submitted to Council from all relevant service providers
              which certifies that the development has met the requirements of this Decision
              Notice and all applicable legislation at the time of construction.
              Easements
        23.   Unless otherwise agreed in writing by the relevant service provider, any public or
              third party infrastructure located on the subject site must be placed within an
              easement registered against the title of the property.




                                                                                 Page 17 of 22

Section 18

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


        24.   All easements must be designed in accordance with the planning scheme and
              granted at no cost to the Grantee. Where the Grantee is Council or a service
              authority, the easement documentation must be in accordance with the Grantee’s
              standard easement terms. Draft easement documentation must be submitted to
              Council for endorsement.
        25.   All works must be kept clear of any existing or proposed easements on the
              subject land, unless agreed otherwise in writing by the Grantee.
              Earthworks and Retaining Walls
        26.   All fill and associated batters must be undertaken in accordance with an
              Operational Works approval, and contained entirely within the subject site unless
              written permission from the respective landowner(s) is provided to Council.
        27.   All retaining walls must be designed and constructed in accordance with the
              planning scheme and must be certified by an RPEQ where exceeding 1.0m in
              height. All retaining walls that are publicly accessible and exceed 1.0m in height
              must be fitted with a commercial grade safety fence.
              Damage to Services and Assets
        28.   Any damage caused to existing services and assets as a result of the
              development works must be repaired at no cost to the asset owner at the
              following times:
              a.    where the damage would cause a hazard to pedestrian or vehicle safety,
                    immediately; or
              b.    where otherwise, upon completion of the works associated with the
                    development.
              Any repair work which proposes to alter the alignment or level of existing services
              and assets must first be referred to the relevant service authority for approval.
              Landscaping Works
        29.   The development site must be landscaped prior to the commencement of use.
              The works must be undertaken in accordance with an Operational Works
              approval and the Noosa Plan for that specific area and must include in particular:
              a.    the landscape areas shown on the approved Site Plan/Floor Plan prepared
                    by Andrew McKellar Design dated 14.06.2017.
              b.    a minimum 2-metre-wide landscaping strip along the Ernest and Hilton road
                    frontage of the subject site, exclusive of the access driveway, generally
                    uncompromised by infrastructure items.
              c.    Any retaining walls must be setback from the front boundaries as shown
                    on the Approved Plans and screened with landscaping. Landscaping plans
                    must clearly show any retaining structure and adequately demonstrate how
                    these structures will be permanently screened with native vegetation.
              d.    all letterboxes located inside the development or in a position which does
                    not visually dominate the frontage.
              e.    details of the rendered wall finish on the Hilton terrace frontage, which can
                    include stone facing or other natural looking finishes and complement the
                    proposed landscaping.


                                                                                  Page 18 of 22

Section 19

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                 13 NOVEMBER 2017


              f.    sub-terrain tree planting area demonstrating at least 4m³ area of structured
                    soils per tree is available for root growth and is not subject to compaction.
              g.    Provision of 100L Melaleuca quinquenervia along the frontage.
              h.    Details and depths of all landscaping soils, especially where subject to
                    compaction relating to filling of the site.
              i.    Plant selection generally as shown on the landscape documentation.
              j.    Bio-basin landscape plants must include a mixture of at least five of the
                    following species for planting in the bio-retention basin extended detention
                    surface at a minimum density of 8 plants/m²:
                    i.     Carex appressa
                    ii.    Carex fascicularis
                    iii.   Ficinia nodosa
                    iv.    Juncus usitatis
                    v.     Lomandra longifolia
                    vi.    Ghania sieberiana
        30.   All landscape works must be established and maintained in accordance with the
              approved design for the life of the development, and in a manner that ensures
              healthy, sustained and vigorous plant growth. All plant material must be allowed
              to grow to full form and be refurbished when its life expectancy is reached.
        31.   All landscape works must be maintained generally in accordance with the
              approved design for the life of the development.
              Stormwater Drainage
        32.   The site must be provided with a stormwater drainage system connecting to a
              lawful point of discharge. The works must be undertaken in accordance with an
              Operational Works approval and be generally in accordance with the submitted
              Stormwater Management Plan - Revision A dated 19 April 2017, prepared by
              Switchback 48 Consulting.
        33.   Stormwater runoff from the development must be disposed of on-site without
              causing scour or damage to the subject site or any adjoining property. Plans
              submitted for the Operational Works approval must include calculations in
              accordance with Queensland Urban Drainage Manual for any overland flow
              discharge areas to confirm that scour will not result from the development.
        34.   A stormwater quality treatment system must be provided for the development.
              The works must be undertaken in accordance with an Operational Works
              approval and the Bio-retention Technical Design Guidelines (Water by Design,
              2012), and must include in particular:
               a.   stormwater quality treatment devices of a size and location of 30m2 plus
                    25m2 generally in accordance with those shown in section 2 of the of the
                    Stormwater Management Plan for 11-19 Hilton Terrace Tewantin by
                    Switchback Consulting, dated 19 April 2017.
               b.   Bio-retention devices which:
                    i.     are designed generally in accordance with the Water by Design
                           Technical Design Guidelines for bio-retention basins


                                                                                 Page 19 of 22

Section 20

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                13 NOVEMBER 2017


                   ii.    are provided with a free-draining outlet from the sub-soil drainage
                          system
                   iii.   swales which are designed in accordance with the Water Sensitive
                          Urban Design Technical Design Guidelines for South East
                          Queensland
                   iv.    have batters around the entire perimeter, or where demonstrated that
                          is not feasible, have retaining structures only of the maximum size
                          recommended within the Water by Design Technical Design
                          Guidelines for bio-retention basins.
        35.   All stormwater quality treatment devices must be maintained in accordance with
              the Water by Design (2009) - Maintaining Vegetated Stormwater Assets (Version
              1). A copy of this document must be retained on the site together with the
              approved Operational Works drawings for the stormwater quality treatment
              system and a detailed life cycle costing of the system attached as an addendum.
              Records of all maintenance activities undertaken must be kept and made
              available to Council upon request.
        36.   Any proposed Community Management Statement required for the development
              must include the Water by Design (2009) – Maintaining Vegetated Stormwater
              Assets (Version 1) document and must include the full cost of maintaining the
              system in accordance with that document.
        37.   The applicant must submit plans for approval with the operational works
              application for the inclusion of educational signage or stencilling to be
              incorporated within the development to ensure patrons are reminded to minimise
              waste and place it in bins.
              Stormwater Harvesting
        38.   Operating underground stormwater harvesting tanks must be provided for the
              development. The tanks must be provided in accordance with an Operational
              Works approval and must include in particular:
              a.   a total tank capacity of a size suitable to maintain expected non-potable
                   and outdoor uses for a 2 month period without rain.
              b.   a minimum catchment of 50% of the building roof area.
              c.   re-use of harvested rainwater for internal non-potable uses and outdoor
                   uses.
              d.   stormwater harvesting tanks are to be located to the rear of the building.
        39.   Certification must be submitted to Council from a qualified person which certifies
              that the rainwater collection tank/s and associated reticulation has/have been
              installed in accordance with the requirements of this Decision Notice.
              Acid Sulfate Soils
        40.   All works must be carried out in accordance with an Acid Sulfate Soil and
              Groundwater Management Plan for the development prepared by a suitably
              qualified person and referenced in a Development Permit for Operational Works.
              The Acid Sulfate Soil and Groundwater Management Plan submitted with the
              application for Operational Works must detail:




                                                                                 Page 20 of 22

Section 21

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                                    13 NOVEMBER 2017


               a.    Management necessary for the proposed filling to avoid any impacts of the
                     Potential Acid Sulfate Soils identified on the site – in particular impacts
                     related to compacting Acid Sulfate Soils into the groundwater table and
                     releasing water contaminants.
               b.    design measures necessary to prevent any oxidation of the potential acid
                     sulfate soils or transfer of acid sulfate soil leachates via dewatering of
                     groundwater through underground pipe bedding material.
               c.    Any other matters necessary to prevent the oxidation of potential acid
                     sulfate soils or release of Acid Sulfate Soil related water contaminants.
         41.   All waters, including stormwater runoff, groundwater seepage and leachate from
               acid sulfate soils must achieve the following quality prior to release from the site:
               a.    a pH range of 6.5-8.5 pH units
               b.    50mg/L maximum total suspended solids concentration
               c.    0.3mg/L maximum total iron concentration
               d.    0.2mg/L maximum total aluminium concentration
               e.    no visible plume at either the point of release from the site or within a
                     waterway
               Waste Disposal
         42.   The developer must provide waste storage and disposal facilities in accordance
               with Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and
               Commercial and Industrial Premises”. The facilities must include an external
               impervious area correctly sized for all refuse and recycling containers and
               suitably screened from public places and neighbouring properties. A bin wash
               area is required with a cold-water tap, hose and drain outlet connected to sewer,
               via a bucket trap. The drain outlet must be designed to prevent storm water entry
               to the sewerage system.
         43.   Refuse containers must be provided in accordance with the requirements of the
               Environmental Protection (Interim Waste) Regulation 1996 and (Waste
               Management) Regulation 2000, for the storage and collection of refuse.
         44.   Public bins must be provided throughout the car park to reduce littering. Bins
               provided must be for refuse and recycling and be decanted into the bulk bins by
               the site operators.
    B.   Enter into an Infrastructure Agreement with the applicant that provides for the
         acquisition of part of the site, compensation for this land acquisition, frontage works
         being undertaken by Council, demolishing of the existing building and car parking in
         lieu of 8 on-site car parking spaces.
                                                                                          Carried.




                                                                                    Page 21 of 22

Section 22

RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING                                             13 NOVEMBER 2017


6   ASSET  MANAGEMENT              AND   DESIGN     SERVICES       TEAM     RESOURCING
    ARRANGEMENTS
    Committee Recommendation
    Moved:          Cr Jackson
    Seconded:       Cr Glasgow
    That Council note the report by the Asset Planning Manager and Infrastructure Planning,
    Design and Delivery Manager to the General Committee Meeting dated 13 November 2017
    and approve changes to Council’s organisational structure as detailed in the report.
                                                                                  Carried.


7   FINANCIAL PERFORMANCE REPORT - OCTOBER 2017
    Committee Recommendation
    Moved:          Cr Pardon
    Seconded:       Cr Jurisevic
    That Council note the report by the Manager Financial Services to the General Committee
    Meeting dated 13 November 2017 outlining the October year to date financial performance
    against budget.
                                                                                  Carried.




                                                                             Page 22 of 22

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.