1.

“12.

13.

14.

The swimming pool shall be licensed annuelly with the Council's Health:
Department in accordance with the provisions of Chapter 42 of

. Council's By-Laws.

Prior ‘to occupation ‘of the building and prior to Council ‘sealing
Building Units Plans for the proposed development, a temporary or.
permanent road closure is to be effected in respect of any driveway
area proposed to be located within the Edgar Bennett Avenue road
reserve. Evidence of a formal application in this regard is to be
lodged prior to the issue of a Building Approval.

No fencing or security gates are to be erected within the road reserve
until such times as the relevant road closure is effected.

The following works are to be completed to the satisfaction of the
Shire Engineer and shall require the submission of detailed
engineering drawings submitted by a Registered Civil Engineer and
approved by the Shire Engineer prior to the issue of building
approval :-

(a) Having regard to previous geotechnical engineering reports “and
recommendations, Council requires the applicant to construct a
retaining wall along the Noosa Drive frontage of the site. Such
wall is required to stabilise the toe of the slope and protect
Noosa Drive in the event of failure of the slope due to building
works on the site. The wall shall be located approximately 5.0
m. from the edge of the existing Noosa Drive construction and
shall run approximately parallel to the western boundary of the

site. The wall shall extend to include the whole of the
projected frontage of the site by extending the southern side
boundary. The approved retaining wall construction shall be

completed prior to building works commencing on the site. The
height and foundstion details of the retaining well shall be
. fixed by a Registered Geotechnical Engineer and will require
approval of the Shire Engineer prior to construction works

commencing. These works are required in lieu of a contribution
towards road improvements in accordance with Council's Noosa Hill
Policy.

{b) Connection to Council's existing water supply reticulation at the
Developer's expense. The applicants" Hydraulic consultants shall
design the internal woeter reticulation system to provide a
service to each unit in accordance with the Department of Local
Government.'s Guidelines. Any upgrading or extensions required to
Council's existing system to provide the required flow rates
shall be at the Developer's full expense.

(c) Aécess to the site is to be constructed in accordance with
Council's Policy and standard drawings. The design details shall
be accompanied by advice from SEQEB in regard to relocation of
its existing services in the Edgar Bennett Avenue road reserve.
All alterations to existing services necessitated by the access
construction shall be et the full expense of the developer.

 
Log in to download the original file

TPC 1947 - Approval Letter.tif · 342 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.