5.0 STORMWATER MANAGEMENT
5.1 Legal Point of Discharge
Engineering Drawing C6535/24/SK07 attached as Appendix C indicates the Legal Point of
Discharge (LPOD) and proposed stormwater drainage network for the development site.
Under existing conditions, stormwater runoff is conveyed in two directions
- A westerly direction as sheet and channel flow to the western boundary and into
the adjoining property to the west.
- A northerly direction into the existing flow path, crossing Hoy Road at the northern
boundary of the site.
The site currently accepts stormwater runoff via the existing flow path from minor
upstream external catchments to the south and east. It is proposed not to change the
existing runoff regime and maintain the existing flow path in its current form, except for
works proposed to the Hoy Road crossing of the central flow path.
It is proposed to upgrade the drainage under the existing causeway crossing of Hoy Road
where the central flow path passes to the north. The causeway currently features a
600mm diameter reinforced concrete pipe (RCP). It is proposed to raise the causeway by
100mm and provide 5 x 750mm diameter RCP’s. This will provide immunity to the
causeway for events up to and including the 10% AEP storm event.
This approach is considered appropriate for the development site on the following
grounds;
- The existing waterway downstream of the site is heavily vegetated. No discernible
adverse impacts will result from proposed development works.
7
Document Set ID: 23448644
Version: 1, Version Date: 13/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.