Delegated Report - Code - Planning OPW26 0069 (As Published)

of 17
               DURING CONSTRUCTION
                      Engineering
               15.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               16.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               17.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      the approved plans/documents and conditions detailed in this Decision Notice;
                      b.      the relevant conditions of the higher order Material Change of Use approval viz.
                              MCU25/0118 to which this approval relates; and
                      c.      all relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines.
                      Landscaping Works
               18.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice.
                      (* Refer to Advisory Note)
               19.    Landscape works must:
                      a.      Ensure amenity or sales signage and ancillary infrastructure is not installed within the
                              road reserve.
                      b.      Ensure permanent irrigation is not installed within the road reserve; and
                      c.      Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
                              foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
                              applied to all planting areas to ensure a minimum 100mm depth once settled.
               20.    Turfed areas must be must be free of pest, diseases and weeds and level with adjoining
                      surfaces.
               21.    Soil for landscaping must:
                      a.      Provide for healthy and sustained site specific vegetation performance; and
                      b.      Comply with AS4419, Soils for landscaping and garden use.
                      Roadworks (External Roadworks & Road Widening Works)
               22.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.
                      Pavement Design and Construction
               23.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.




                                                                                                        Page 11 of 17

Document Set ID: 25035493
Version: 2, Version Date: 07/08/2026

Log in to download the original (Delegated Report - Code - Planning OPW26 0069 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.