DURING CONSTRUCTION
Engineering
15. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
16. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
17. All works must be constructed and work procedure undertaken in accordance with:
a. the approved plans/documents and conditions detailed in this Decision Notice;
b. the relevant conditions of the higher order Material Change of Use approval viz.
MCU25/0118 to which this approval relates; and
c. all relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
Landscaping Works
18. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice.
(* Refer to Advisory Note)
19. Landscape works must:
a. Ensure amenity or sales signage and ancillary infrastructure is not installed within the
road reserve.
b. Ensure permanent irrigation is not installed within the road reserve; and
c. Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
applied to all planting areas to ensure a minimum 100mm depth once settled.
20. Turfed areas must be must be free of pest, diseases and weeds and level with adjoining
surfaces.
21. Soil for landscaping must:
a. Provide for healthy and sustained site specific vegetation performance; and
b. Comply with AS4419, Soils for landscaping and garden use.
Roadworks (External Roadworks & Road Widening Works)
22. All pavement widening or construction of new pavement must join neatly to the existing
pavement so that there are no irregularities in line or level resulting at or adjacent to the join
for the length of the construction. Where necessary the existing pavement must be brought
to a satisfactory standard to allow for the above.
Pavement Design and Construction
23. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Page 11 of 17
Document Set ID: 25035493
Version: 2, Version Date: 07/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Delegated Report - Code - Planning OPW26 0069 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.